Time and Work
MCQs Math


Question:     If Paul can finish the work in 36 days and Larry can finish the same work in 39 days, then in how many days both can finish the work together?


Correct Answer  18 18/25 days or 18.72 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Paul = 36 days

And, the number of days to finish the same work by Larry = 39 days

Thus, the number of days to finish the work by Paul and Larry together = ?

Here,

∵ In 36 days the work done by Paul = 1

∴ In 1 day, the work done by Paul = 1/36 part

Similarly,

∵ In 39 days the work done by Larry = 1

∴ In 1 day, the work done by Larry = 1/39 part

Now, in 1 day, the work done by Paul and Larry together

= In 1 day work done by Paul + In 1 day the work done by Larry

= 1/36 + 1/39

= 13 + 12/468

= 25/468 part of work

This means in 1 day, 25/468 part of work is done by Paul and Larry working together.

Now, the number of days required to finish 25/468 part of work by Paul + Larry working together = 1

∴ the number of days required to finish 1 work by Paul + Larry together

= 1/25/468

= 1 × 468/25 = 468/25 days

= 18 18/25 days = or 18.72 days

Thus, Paul and Larry working together will finish the work in 18 18/25 days = or 18.72 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Paul = 36 days

And the number of days required to finish the same work by Larry = 39 days

Thus, the number of days required to finish the work Paul and Larry working together = ?

Here a = 36 days

And, b = 39 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Paul and Larry working together

= 36 × 39/36 + 39 days

= 1404/75 days

= 1404 ÷ 3/75 ÷ 3 = 468/25 days

= 18 18/25 days or 18.72

Thus, Paul and Larry together will finish the work in 18 18/25 days or 18.72 days Answer


Similar Questions

(1) Daniel can finish a work in 27 days. Anthony can finish the same work in 32 days while Mark can finish the work in 37 days. How long will it take to finish it if they work together?

(2) If Mark can finish the work in 33 days and Jacob can finish the same work in 38 days, then in how many days both can finish the work together?

(3) If Emma can finish the work in 80 days and Jordan can finish the same work in 85 days, then in how many days both can finish the work together?

(4) If Gary can finish the work in 67 days and Christian can finish the same work in 72 days, then in how many days both can finish the work together?

(5) If Justin can finish the work in 79 days and Jesse can finish the same work in 84 days, then in how many days both can finish the work together?

(6) Donna can finish a work in 38 days. Michelle can finish the same work in 39 days while Carol can finish the work in 40 days. How long will it take to finish it if they work together?

(7) If Jessica can finish the work in 20 days and Paul can finish the same work in 25 days, then in how many days both can finish the work together?

(8) If Angela can finish the work in 70 days and Terry can finish the same work in 75 days, then in how many days both can finish the work together?

(9) If Pamela can finish the work in 78 days and Dylan can finish the same work in 83 days, then in how many days both can finish the work together?

(10) If Steven can finish the work in 34 days and Jonathan can finish the same work in 38 days, then in how many days both can finish the work together?