If Michelle can finish the work in 41 days and Samuel can finish the same work in 44 days, then in how many days both can finish the work together?
Correct Answer
21 19/85 days or 21.224 days
Solution And Explanation
Solution
Given,
The number of days to finish the work by Michelle = 41 days
And, the number of days to finish the same work by Samuel = 44 days
Thus, the number of days to finish the work by Michelle and Samuel together = ?
Here,
∵ In 41 days the work done by Michelle = 1
∴ In 1 day, the work done by Michelle = 1/41 part
Similarly,
∵ In 44 days the work done by Samuel = 1
∴ In 1 day, the work done by Samuel = 1/44 part
Now, in 1 day, the work done by Michelle and Samuel together
= In 1 day work done by Michelle + In 1 day the work done by Samuel
= 1/41 + 1/44
= 44 + 41/1804
= 85/1804 part of work
This means in 1 day, 85/1804 part of work is done by Michelle and Samuel working together.
Now, the number of days required to finish 85/1804 part of work by Michelle + Samuel working together = 1
∴ the number of days required to finish 1 work by Michelle + Samuel together
= 1/85/1804
= 1 × 1804/85 = 1804/85 days
= 21 19/85 days = or 21.224 days
Thus, Michelle and Samuel working together will finish the work in 21 19/85 days = or 21.224 days Answer
Shortcut Trick to solve the problems based on time and work using formula
Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.
Here given,
The number of days required to finish the work by Michelle = 41 days
And the number of days required to finish the same work by Samuel = 44 days
Thus, the number of days required to finish the work Michelle and Samuel working together = ?
Here a = 41 days
And, b = 44 days
Thus, using formula a × b/a + b days
The number of days required to finish the work when Michelle and Samuel working together
= 41 × 44/41 + 44 days
= 1804/85 days
= 21 19/85 days or 21.224
Thus, Michelle and Samuel together will finish the work in 21 19/85 days or 21.224 days Answer
Similar Questions
(1) Kimberly can finish a work in 34 days. Emily can finish the same work in 35 days while Donna can finish the work in 36 days. How long will it take to finish it if they work together?
(2) If Andrew can finish the work in 38 days and Scott can finish the same work in 41 days, then in how many days both can finish the work together?
(3) If Sarah can finish the work in 19 days and Joshua can finish the same work in 23 days, then in how many days both can finish the work together?
(4) If Betty can finish the work in 27 days and Jason can finish the same work in 31 days, then in how many days both can finish the work together?
(5) If Carol can finish the work in 43 days and Alexander can finish the same work in 46 days, then in how many days both can finish the work together?
(6) If Amanda can finish the work in 48 days and Patrick can finish the same work in 53 days, then in how many days both can finish the work together?
(7) If Andrew can finish the work in 38 days and Scott can finish the same work in 42 days, then in how many days both can finish the work together?
(8) If Lisa can finish the work in 23 days and George can finish the same work in 26 days, then in how many days both can finish the work together?
(9) Rebecca can finish a work in 58 days. Laura can finish the same work in 63 days while Cynthia can finish the work in 68 days. How long will it take to finish it if they work together?
(10) If Robert can finish the work in 7 days and David can finish the same work in 12 days, then in how many days both can finish the work together?