Time and Work
MCQs Math


Question:     If Kevin can finish the work in 44 days and Frank can finish the same work in 47 days, then in how many days both can finish the work together?


Correct Answer  22 66/91 days or 22.725 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Kevin = 44 days

And, the number of days to finish the same work by Frank = 47 days

Thus, the number of days to finish the work by Kevin and Frank together = ?

Here,

∵ In 44 days the work done by Kevin = 1

∴ In 1 day, the work done by Kevin = 1/44 part

Similarly,

∵ In 47 days the work done by Frank = 1

∴ In 1 day, the work done by Frank = 1/47 part

Now, in 1 day, the work done by Kevin and Frank together

= In 1 day work done by Kevin + In 1 day the work done by Frank

= 1/44 + 1/47

= 47 + 44/2068

= 91/2068 part of work

This means in 1 day, 91/2068 part of work is done by Kevin and Frank working together.

Now, the number of days required to finish 91/2068 part of work by Kevin + Frank working together = 1

∴ the number of days required to finish 1 work by Kevin + Frank together

= 1/91/2068

= 1 × 2068/91 = 2068/91 days

= 22 66/91 days = or 22.725 days

Thus, Kevin and Frank working together will finish the work in 22 66/91 days = or 22.725 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Kevin = 44 days

And the number of days required to finish the same work by Frank = 47 days

Thus, the number of days required to finish the work Kevin and Frank working together = ?

Here a = 44 days

And, b = 47 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Kevin and Frank working together

= 44 × 47/44 + 47 days

= 2068/91 days

= 22 66/91 days or 22.725

Thus, Kevin and Frank together will finish the work in 22 66/91 days or 22.725 days Answer


Similar Questions

(1) If Jennifer can finish the work in 29 days and Joseph can finish the same work in 45 days, then in how many days both can finish the work together?

(2) If Elizabeth can finish the work in 11 days and Daniel can finish the same work in 14 days, then in how many days both can finish the work together?

(3) If Lisa can finish the work in 23 days and George can finish the same work in 26 days, then in how many days both can finish the work together?

(4) If William can finish the work in 12 days and Matthew can finish the same work in 15 days, then in how many days both can finish the work together?

(5) If Paul can finish the work in 39 days and Larry can finish the same work in 44 days, then in how many days both can finish the work together?

(6) Ryan can finish a work in 63 days. Gary can finish the same work in 68 days while Nicholas can finish the work in 73 days. How long will it take to finish it if they work together?

(7) If Barbara can finish the work in 13 days and Anthony can finish the same work in 16 days, then in how many days both can finish the work together?

(8) If Jessica can finish the work in 17 days and Paul can finish the same work in 21 days, then in how many days both can finish the work together?

(9) George can finish a work in 47 days. Timothy can finish the same work in 48 days while Ronald can finish the work in 49 days. How long will it take to finish it if they work together?

(10) If Gary can finish the work in 67 days and Christian can finish the same work in 72 days, then in how many days both can finish the work together?