Time and Work
MCQs Math


Question:     If Robert can finish the work in 7 days and David can finish the same work in 12 days, then in how many days both can finish the work together?


Correct Answer  4 8/19 days or 4.421 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Robert = 7 days

And, the number of days to finish the same work by David = 12 days

Thus, the number of days to finish the work by Robert and David together = ?

Here,

∵ In 7 days the work done by Robert = 1

∴ In 1 day, the work done by Robert = 1/7 part

Similarly,

∵ In 12 days the work done by David = 1

∴ In 1 day, the work done by David = 1/12 part

Now, in 1 day, the work done by Robert and David together

= In 1 day work done by Robert + In 1 day the work done by David

= 1/7 + 1/12

= 12 + 7/84

= 19/84 part of work

This means in 1 day, 19/84 part of work is done by Robert and David working together.

Now, the number of days required to finish 19/84 part of work by Robert + David working together = 1

∴ the number of days required to finish 1 work by Robert + David together

= 1/19/84

= 1 × 84/19 = 84/19 days

= 4 8/19 days = or 4.421 days

Thus, Robert and David working together will finish the work in 4 8/19 days = or 4.421 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Robert = 7 days

And the number of days required to finish the same work by David = 12 days

Thus, the number of days required to finish the work Robert and David working together = ?

Here a = 7 days

And, b = 12 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Robert and David working together

= 7 × 12/7 + 12 days

= 84/19 days

= 4 8/19 days or 4.421

Thus, Robert and David together will finish the work in 4 8/19 days or 4.421 days Answer


Similar Questions

(1) If Gregory can finish the work in 89 days and Alan can finish the same work in 94 days, then in how many days both can finish the work together?

(2) Joshua can finish a work in 43 days. Kevin can finish the same work in 48 days while Brian can finish the work in 53 days. How long will it take to finish it if they work together?

(3) Anna can finish a work in 74 days. Pamela can finish the same work in 79 days while Emma can finish the work in 84 days. How long will it take to finish it if they work together?

(4) If Margaret can finish the work in 32 days and Ryan can finish the same work in 37 days, then in how many days both can finish the work together?

(5) Amanda can finish a work in 48 days. Melissa can finish the same work in 53 days while Deborah can finish the work in 58 days. How long will it take to finish it if they work together?

(6) Catherine can finish a work in 100 days. Heather can finish the same work in 105 days while Diane can finish the work in 110 days. How long will it take to finish it if they work together?

(7) If Karen can finish the work in 24 days and Kevin can finish the same work in 29 days, then in how many days both can finish the work together?

(8) If Scott can finish the work in 81 days and Bryan can finish the same work in 86 days, then in how many days both can finish the work together?

(9) If Emma can finish the work in 80 days and Jordan can finish the same work in 85 days, then in how many days both can finish the work together?

(10) If David can finish the work in 10 days and Christopher can finish the same work in 13 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©