Time and Work
MCQs Math


Question:     If Robert can finish the work in 7 days and David can finish the same work in 12 days, then in how many days both can finish the work together?


Correct Answer  4 8/19 days or 4.421 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Robert = 7 days

And, the number of days to finish the same work by David = 12 days

Thus, the number of days to finish the work by Robert and David together = ?

Here,

∵ In 7 days the work done by Robert = 1

∴ In 1 day, the work done by Robert = 1/7 part

Similarly,

∵ In 12 days the work done by David = 1

∴ In 1 day, the work done by David = 1/12 part

Now, in 1 day, the work done by Robert and David together

= In 1 day work done by Robert + In 1 day the work done by David

= 1/7 + 1/12

= 12 + 7/84

= 19/84 part of work

This means in 1 day, 19/84 part of work is done by Robert and David working together.

Now, the number of days required to finish 19/84 part of work by Robert + David working together = 1

∴ the number of days required to finish 1 work by Robert + David together

= 1/19/84

= 1 × 84/19 = 84/19 days

= 4 8/19 days = or 4.421 days

Thus, Robert and David working together will finish the work in 4 8/19 days = or 4.421 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Robert = 7 days

And the number of days required to finish the same work by David = 12 days

Thus, the number of days required to finish the work Robert and David working together = ?

Here a = 7 days

And, b = 12 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Robert and David working together

= 7 × 12/7 + 12 days

= 84/19 days

= 4 8/19 days or 4.421

Thus, Robert and David together will finish the work in 4 8/19 days or 4.421 days Answer


Similar Questions

(1) If Sarah can finish the work in 22 days and Joshua can finish the same work in 27 days, then in how many days both can finish the work together?

(2) If Kevin can finish the work in 47 days and Frank can finish the same work in 52 days, then in how many days both can finish the work together?

(3) If Barbara can finish the work in 13 days and Anthony can finish the same work in 16 days, then in how many days both can finish the work together?

(4) If Emily can finish the work in 40 days and Justin can finish the same work in 45 days, then in how many days both can finish the work together?

(5) If Ashley can finish the work in 33 days and Eric can finish the same work in 36 days, then in how many days both can finish the work together?

(6) Frank can finish a work in 93 days. Raymond can finish the same work in 98 days while Jack can finish the work in 103 days. How long will it take to finish it if they work together?

(7) Daniel can finish a work in 27 days. Anthony can finish the same work in 32 days while Mark can finish the work in 37 days. How long will it take to finish it if they work together?

(8) If Jessica can finish the work in 17 days and Paul can finish the same work in 20 days, then in how many days both can finish the work together?

(9) If Charles can finish the work in 23 days and Kenneth can finish the same work in 28 days, then in how many days both can finish the work together?

(10) Donald can finish a work in 31 days. Steven can finish the same work in 32 days while Paul can finish the work in 33 days. How long will it take to finish it if they work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©