Time and Work
MCQs Math


Question:     If John can finish the work in 9 days and Richard can finish the same work in 14 days, then in how many days both can finish the work together?


Correct Answer  5 11/23 days or 5.478 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by John = 9 days

And, the number of days to finish the same work by Richard = 14 days

Thus, the number of days to finish the work by John and Richard together = ?

Here,

∵ In 9 days the work done by John = 1

∴ In 1 day, the work done by John = 1/9 part

Similarly,

∵ In 14 days the work done by Richard = 1

∴ In 1 day, the work done by Richard = 1/14 part

Now, in 1 day, the work done by John and Richard together

= In 1 day work done by John + In 1 day the work done by Richard

= 1/9 + 1/14

= 14 + 9/126

= 23/126 part of work

This means in 1 day, 23/126 part of work is done by John and Richard working together.

Now, the number of days required to finish 23/126 part of work by John + Richard working together = 1

∴ the number of days required to finish 1 work by John + Richard together

= 1/23/126

= 1 × 126/23 = 126/23 days

= 5 11/23 days = or 5.478 days

Thus, John and Richard working together will finish the work in 5 11/23 days = or 5.478 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by John = 9 days

And the number of days required to finish the same work by Richard = 14 days

Thus, the number of days required to finish the work John and Richard working together = ?

Here a = 9 days

And, b = 14 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when John and Richard working together

= 9 × 14/9 + 14 days

= 126/23 days

= 5 11/23 days or 5.478

Thus, John and Richard together will finish the work in 5 11/23 days or 5.478 days Answer


Similar Questions

(1) Alexander can finish a work in 91 days. Patrick can finish the same work in 96 days while Raymond can finish the work in 101 days. How long will it take to finish it if they work together?

(2) If Daniel can finish the work in 24 days and Timothy can finish the same work in 27 days, then in how many days both can finish the work together?

(3) If Kenneth can finish the work in 42 days and Gregory can finish the same work in 46 days, then in how many days both can finish the work together?

(4) If Michelle can finish the work in 44 days and Samuel can finish the same work in 49 days, then in how many days both can finish the work together?

(5) If Dorothy can finish the work in 47 days and Jack can finish the same work in 50 days, then in how many days both can finish the work together?

(6) If Betty can finish the work in 27 days and Jason can finish the same work in 31 days, then in how many days both can finish the work together?

(7) If Laura can finish the work in 62 days and Kyle can finish the same work in 67 days, then in how many days both can finish the work together?

(8) If Jason can finish the work in 59 days and Douglas can finish the same work in 64 days, then in how many days both can finish the work together?

(9) If Jacob can finish the work in 65 days and Noah can finish the same work in 70 days, then in how many days both can finish the work together?

(10) John can finish a work in 5 days. Michael can finish the same work in 6 days while David can finish the work in 7 days. How long will it take to finish it if they work together?