Time and Work
MCQs Math


Question:     If Joseph can finish the work in 19 days and Steven can finish the same work in 24 days, then in how many days both can finish the work together?


Correct Answer  10 26/43 days or 10.605 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Joseph = 19 days

And, the number of days to finish the same work by Steven = 24 days

Thus, the number of days to finish the work by Joseph and Steven together = ?

Here,

∵ In 19 days the work done by Joseph = 1

∴ In 1 day, the work done by Joseph = 1/19 part

Similarly,

∵ In 24 days the work done by Steven = 1

∴ In 1 day, the work done by Steven = 1/24 part

Now, in 1 day, the work done by Joseph and Steven together

= In 1 day work done by Joseph + In 1 day the work done by Steven

= 1/19 + 1/24

= 24 + 19/456

= 43/456 part of work

This means in 1 day, 43/456 part of work is done by Joseph and Steven working together.

Now, the number of days required to finish 43/456 part of work by Joseph + Steven working together = 1

∴ the number of days required to finish 1 work by Joseph + Steven together

= 1/43/456

= 1 × 456/43 = 456/43 days

= 10 26/43 days = or 10.605 days

Thus, Joseph and Steven working together will finish the work in 10 26/43 days = or 10.605 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Joseph = 19 days

And the number of days required to finish the same work by Steven = 24 days

Thus, the number of days required to finish the work Joseph and Steven working together = ?

Here a = 19 days

And, b = 24 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Joseph and Steven working together

= 19 × 24/19 + 24 days

= 456/43 days

= 10 26/43 days or 10.605

Thus, Joseph and Steven together will finish the work in 10 26/43 days or 10.605 days Answer


Similar Questions

(1) If Kenneth can finish the work in 42 days and Gregory can finish the same work in 46 days, then in how many days both can finish the work together?

(2) Kevin can finish a work in 43 days. Brian can finish the same work in 44 days while George can finish the work in 45 days. How long will it take to finish it if they work together?

(3) If Joshua can finish the work in 43 days and Benjamin can finish the same work in 48 days, then in how many days both can finish the work together?

(4) If Nancy can finish the work in 25 days and Ronald can finish the same work in 28 days, then in how many days both can finish the work together?

(5) If Michelle can finish the work in 44 days and Samuel can finish the same work in 49 days, then in how many days both can finish the work together?

(6) Laura can finish a work in 62 days. Kathleen can finish the same work in 67 days while Amy can finish the work in 72 days. How long will it take to finish it if they work together?

(7) Lisa can finish a work in 26 days. Betty can finish the same work in 31 days while Margaret can finish the work in 36 days. How long will it take to finish it if they work together?

(8) If Mark can finish the work in 33 days and Jacob can finish the same work in 38 days, then in how many days both can finish the work together?

(9) If Barbara can finish the work in 35 days and Anthony can finish the same work in 51 days, then in how many days both can finish the work together?

(10) If Kenneth can finish the work in 45 days and Gregory can finish the same work in 50 days, then in how many days both can finish the work together?