Question:     If Joseph can finish the work in 19 days and Steven can finish the same work in 24 days, then in how many days both can finish the work together?


Correct Answer  10 26/43 days or 10.605 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Joseph = 19 days

And, the number of days to finish the same work by Steven = 24 days

Thus, the number of days to finish the work by Joseph and Steven together = ?

Here,

∵ In 19 days the work done by Joseph = 1

∴ In 1 day, the work done by Joseph = 1/19 part

Similarly,

∵ In 24 days the work done by Steven = 1

∴ In 1 day, the work done by Steven = 1/24 part

Now, in 1 day, the work done by Joseph and Steven together

= In 1 day work done by Joseph + In 1 day the work done by Steven

= 1/19 + 1/24

= 24 + 19/456

= 43/456 part of work

This means in 1 day, 43/456 part of work is done by Joseph and Steven working together.

Now, the number of days required to finish 43/456 part of work by Joseph + Steven working together = 1

∴ the number of days required to finish 1 work by Joseph + Steven together

= 1/43/456

= 1 × 456/43 = 456/43 days

= 10 26/43 days = or 10.605 days

Thus, Joseph and Steven working together will finish the work in 10 26/43 days = or 10.605 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Joseph = 19 days

And the number of days required to finish the same work by Steven = 24 days

Thus, the number of days required to finish the work Joseph and Steven working together = ?

Here a = 19 days

And, b = 24 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Joseph and Steven working together

= 19 × 24/19 + 24 days

= 456/43 days

= 10 26/43 days or 10.605

Thus, Joseph and Steven together will finish the work in 10 26/43 days or 10.605 days Answer


Similar Questions

(1) If Carol can finish the work in 43 days and Alexander can finish the same work in 47 days, then in how many days both can finish the work together?

(2) If Linda can finish the work in 31 days and Charles can finish the same work in 47 days, then in how many days both can finish the work together?

(3) Ashley can finish a work in 36 days. Emily can finish the same work in 41 days while Donna can finish the work in 46 days. How long will it take to finish it if they work together?

(4) If Ashley can finish the work in 33 days and Eric can finish the same work in 36 days, then in how many days both can finish the work together?

(5) Kimberly can finish a work in 34 days. Emily can finish the same work in 35 days while Donna can finish the work in 36 days. How long will it take to finish it if they work together?

(6) Thomas can finish a work in 17 days. Charles can finish the same work in 18 days while Christopher can finish the work in 19 days. How long will it take to finish it if they work together?

(7) If Matthew can finish the work in 26 days and Edward can finish the same work in 30 days, then in how many days both can finish the work together?

(8) If Deborah can finish the work in 54 days and Aaron can finish the same work in 59 days, then in how many days both can finish the work together?

(9) Rebecca can finish a work in 58 days. Laura can finish the same work in 63 days while Cynthia can finish the work in 68 days. How long will it take to finish it if they work together?

(10) If Mark can finish the work in 30 days and Jacob can finish the same work in 34 days, then in how many days both can finish the work together?