Question:     If Jessica can finish the work in 20 days and Paul can finish the same work in 25 days, then in how many days both can finish the work together?


Correct Answer  11 1/9 days or 11.111 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Jessica = 20 days

And, the number of days to finish the same work by Paul = 25 days

Thus, the number of days to finish the work by Jessica and Paul together = ?

Here,

∵ In 20 days the work done by Jessica = 1

∴ In 1 day, the work done by Jessica = 1/20 part

Similarly,

∵ In 25 days the work done by Paul = 1

∴ In 1 day, the work done by Paul = 1/25 part

Now, in 1 day, the work done by Jessica and Paul together

= In 1 day work done by Jessica + In 1 day the work done by Paul

= 1/20 + 1/25

= 5 + 4/100

= 9/100 part of work

This means in 1 day, 9/100 part of work is done by Jessica and Paul working together.

Now, the number of days required to finish 9/100 part of work by Jessica + Paul working together = 1

∴ the number of days required to finish 1 work by Jessica + Paul together

= 1/9/100

= 1 × 100/9 = 100/9 days

= 11 1/9 days = or 11.111 days

Thus, Jessica and Paul working together will finish the work in 11 1/9 days = or 11.111 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Jessica = 20 days

And the number of days required to finish the same work by Paul = 25 days

Thus, the number of days required to finish the work Jessica and Paul working together = ?

Here a = 20 days

And, b = 25 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Jessica and Paul working together

= 20 × 25/20 + 25 days

= 500/45 days

= 500 ÷ 5/45 ÷ 5 = 100/9 days

= 11 1/9 days or 11.111

Thus, Jessica and Paul together will finish the work in 11 1/9 days or 11.111 days Answer


Similar Questions

(1) If Joseph can finish the work in 19 days and Steven can finish the same work in 24 days, then in how many days both can finish the work together?

(2) If Stephanie can finish the work in 56 days and Adam can finish the same work in 61 days, then in how many days both can finish the work together?

(3) Susan can finish a work in 14 days. Jessica can finish the same work in 15 days while Sarah can finish the work in 16 days. How long will it take to finish it if they work together?

(4) If Melissa can finish the work in 52 days and Jerry can finish the same work in 57 days, then in how many days both can finish the work together?

(5) If Ronald can finish the work in 55 days and Jose can finish the same work in 60 days, then in how many days both can finish the work together?

(6) Rebecca can finish a work in 58 days. Laura can finish the same work in 63 days while Cynthia can finish the work in 68 days. How long will it take to finish it if they work together?

(7) If Anthony can finish the work in 28 days and Jeffrey can finish the same work in 31 days, then in how many days both can finish the work together?

(8) Mary can finish a work in 6 days. Jennifer can finish the same work in 11 days while Linda can finish the work in 16 days. How long will it take to finish it if they work together?

(9) If Paul can finish the work in 36 days and Larry can finish the same work in 40 days, then in how many days both can finish the work together?

(10) Amanda can finish a work in 44 days. Dorothy can finish the same work in 45 days while Melissa can finish the work in 46 days. How long will it take to finish it if they work together?