Time and Work
MCQs Math


Question:     If Thomas can finish the work in 21 days and Andrew can finish the same work in 26 days, then in how many days both can finish the work together?


Correct Answer  11 29/47 days or 11.617 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Thomas = 21 days

And, the number of days to finish the same work by Andrew = 26 days

Thus, the number of days to finish the work by Thomas and Andrew together = ?

Here,

∵ In 21 days the work done by Thomas = 1

∴ In 1 day, the work done by Thomas = 1/21 part

Similarly,

∵ In 26 days the work done by Andrew = 1

∴ In 1 day, the work done by Andrew = 1/26 part

Now, in 1 day, the work done by Thomas and Andrew together

= In 1 day work done by Thomas + In 1 day the work done by Andrew

= 1/21 + 1/26

= 26 + 21/546

= 47/546 part of work

This means in 1 day, 47/546 part of work is done by Thomas and Andrew working together.

Now, the number of days required to finish 47/546 part of work by Thomas + Andrew working together = 1

∴ the number of days required to finish 1 work by Thomas + Andrew together

= 1/47/546

= 1 × 546/47 = 546/47 days

= 11 29/47 days = or 11.617 days

Thus, Thomas and Andrew working together will finish the work in 11 29/47 days = or 11.617 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Thomas = 21 days

And the number of days required to finish the same work by Andrew = 26 days

Thus, the number of days required to finish the work Thomas and Andrew working together = ?

Here a = 21 days

And, b = 26 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Thomas and Andrew working together

= 21 × 26/21 + 26 days

= 546/47 days

= 11 29/47 days or 11.617

Thus, Thomas and Andrew together will finish the work in 11 29/47 days or 11.617 days Answer


Similar Questions

(1) If Karen can finish the work in 21 days and Kevin can finish the same work in 25 days, then in how many days both can finish the work together?

(2) Michael can finish a work in 7 days. David can finish the same work in 8 days while William can finish the work in 9 days. How long will it take to finish it if they work together?

(3) If Daniel can finish the work in 24 days and Timothy can finish the same work in 28 days, then in how many days both can finish the work together?

(4) Christopher can finish a work in 25 days. Matthew can finish the same work in 30 days while Anthony can finish the work in 35 days. How long will it take to finish it if they work together?

(5) If Carolyn can finish the work in 96 days and Ralph can finish the same work in 101 days, then in how many days both can finish the work together?

(6) If Sandra can finish the work in 31 days and Gary can finish the same work in 34 days, then in how many days both can finish the work together?

(7) If Gregory can finish the work in 89 days and Alan can finish the same work in 94 days, then in how many days both can finish the work together?

(8) If Scott can finish the work in 81 days and Bryan can finish the same work in 86 days, then in how many days both can finish the work together?

(9) If Carol can finish the work in 46 days and Alexander can finish the same work in 51 days, then in how many days both can finish the work together?

(10) If Michael can finish the work in 8 days and Thomas can finish the same work in 11 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©