Time and Work
MCQs Math


Question:     If Matthew can finish the work in 29 days and Edward can finish the same work in 34 days, then in how many days both can finish the work together?


Correct Answer  15 41/63 days or 15.651 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Matthew = 29 days

And, the number of days to finish the same work by Edward = 34 days

Thus, the number of days to finish the work by Matthew and Edward together = ?

Here,

∵ In 29 days the work done by Matthew = 1

∴ In 1 day, the work done by Matthew = 1/29 part

Similarly,

∵ In 34 days the work done by Edward = 1

∴ In 1 day, the work done by Edward = 1/34 part

Now, in 1 day, the work done by Matthew and Edward together

= In 1 day work done by Matthew + In 1 day the work done by Edward

= 1/29 + 1/34

= 34 + 29/986

= 63/986 part of work

This means in 1 day, 63/986 part of work is done by Matthew and Edward working together.

Now, the number of days required to finish 63/986 part of work by Matthew + Edward working together = 1

∴ the number of days required to finish 1 work by Matthew + Edward together

= 1/63/986

= 1 × 986/63 = 986/63 days

= 15 41/63 days = or 15.651 days

Thus, Matthew and Edward working together will finish the work in 15 41/63 days = or 15.651 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Matthew = 29 days

And the number of days required to finish the same work by Edward = 34 days

Thus, the number of days required to finish the work Matthew and Edward working together = ?

Here a = 29 days

And, b = 34 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Matthew and Edward working together

= 29 × 34/29 + 34 days

= 986/63 days

= 15 41/63 days or 15.651

Thus, Matthew and Edward together will finish the work in 15 41/63 days or 15.651 days Answer


Similar Questions

(1) Margaret can finish a work in 32 days. Ashley can finish the same work in 37 days while Kimberly can finish the work in 42 days. How long will it take to finish it if they work together?

(2) Nicole can finish a work in 82 days. Samantha can finish the same work in 87 days while Katherine can finish the work in 92 days. How long will it take to finish it if they work together?

(3) Samuel can finish a work in 87 days. Alexander can finish the same work in 92 days while Frank can finish the work in 97 days. How long will it take to finish it if they work together?

(4) If Steven can finish the work in 34 days and Jonathan can finish the same work in 37 days, then in how many days both can finish the work together?

(5) If Andrew can finish the work in 41 days and Scott can finish the same work in 46 days, then in how many days both can finish the work together?

(6) John can finish a work in 5 days. Michael can finish the same work in 6 days while David can finish the work in 7 days. How long will it take to finish it if they work together?

(7) Catherine can finish a work in 100 days. Heather can finish the same work in 105 days while Diane can finish the work in 110 days. How long will it take to finish it if they work together?

(8) If Rachel can finish the work in 94 days and Roy can finish the same work in 99 days, then in how many days both can finish the work together?

(9) Thomas can finish a work in 21 days. Christopher can finish the same work in 26 days while Daniel can finish the work in 31 days. How long will it take to finish it if they work together?

(10) Kevin can finish a work in 43 days. Brian can finish the same work in 44 days while George can finish the work in 45 days. How long will it take to finish it if they work together?