Time and Work
MCQs Math


Question:     If Matthew can finish the work in 29 days and Edward can finish the same work in 34 days, then in how many days both can finish the work together?


Correct Answer  15 41/63 days or 15.651 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Matthew = 29 days

And, the number of days to finish the same work by Edward = 34 days

Thus, the number of days to finish the work by Matthew and Edward together = ?

Here,

∵ In 29 days the work done by Matthew = 1

∴ In 1 day, the work done by Matthew = 1/29 part

Similarly,

∵ In 34 days the work done by Edward = 1

∴ In 1 day, the work done by Edward = 1/34 part

Now, in 1 day, the work done by Matthew and Edward together

= In 1 day work done by Matthew + In 1 day the work done by Edward

= 1/29 + 1/34

= 34 + 29/986

= 63/986 part of work

This means in 1 day, 63/986 part of work is done by Matthew and Edward working together.

Now, the number of days required to finish 63/986 part of work by Matthew + Edward working together = 1

∴ the number of days required to finish 1 work by Matthew + Edward together

= 1/63/986

= 1 × 986/63 = 986/63 days

= 15 41/63 days = or 15.651 days

Thus, Matthew and Edward working together will finish the work in 15 41/63 days = or 15.651 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Matthew = 29 days

And the number of days required to finish the same work by Edward = 34 days

Thus, the number of days required to finish the work Matthew and Edward working together = ?

Here a = 29 days

And, b = 34 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Matthew and Edward working together

= 29 × 34/29 + 34 days

= 986/63 days

= 15 41/63 days or 15.651

Thus, Matthew and Edward together will finish the work in 15 41/63 days or 15.651 days Answer


Similar Questions

(1) If Robert can finish the work in 4 days and David can finish the same work in 8 days, then in how many days both can finish the work together?

(2) If Karen can finish the work in 21 days and Kevin can finish the same work in 24 days, then in how many days both can finish the work together?

(3) Jessica can finish a work in 16 days. Sarah can finish the same work in 17 days while Karen can finish the work in 18 days. How long will it take to finish it if they work together?

(4) If Brian can finish the work in 49 days and Raymond can finish the same work in 54 days, then in how many days both can finish the work together?

(5) Laura can finish a work in 62 days. Kathleen can finish the same work in 67 days while Amy can finish the work in 72 days. How long will it take to finish it if they work together?

(6) Susan can finish a work in 18 days. Sarah can finish the same work in 23 days while Karen can finish the work in 28 days. How long will it take to finish it if they work together?

(7) David can finish a work in 13 days. Richard can finish the same work in 18 days while Joseph can finish the work in 23 days. How long will it take to finish it if they work together?

(8) If Michael can finish the work in 8 days and Thomas can finish the same work in 11 days, then in how many days both can finish the work together?

(9) If Nicole can finish the work in 82 days and Billy can finish the same work in 87 days, then in how many days both can finish the work together?

(10) If Elizabeth can finish the work in 14 days and Daniel can finish the same work in 19 days, then in how many days both can finish the work together?