Time and Work
MCQs Math


Question:     If Ashley can finish the work in 36 days and Eric can finish the same work in 41 days, then in how many days both can finish the work together?


Correct Answer  19 13/77 days or 19.169 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Ashley = 36 days

And, the number of days to finish the same work by Eric = 41 days

Thus, the number of days to finish the work by Ashley and Eric together = ?

Here,

∵ In 36 days the work done by Ashley = 1

∴ In 1 day, the work done by Ashley = 1/36 part

Similarly,

∵ In 41 days the work done by Eric = 1

∴ In 1 day, the work done by Eric = 1/41 part

Now, in 1 day, the work done by Ashley and Eric together

= In 1 day work done by Ashley + In 1 day the work done by Eric

= 1/36 + 1/41

= 41 + 36/1476

= 77/1476 part of work

This means in 1 day, 77/1476 part of work is done by Ashley and Eric working together.

Now, the number of days required to finish 77/1476 part of work by Ashley + Eric working together = 1

∴ the number of days required to finish 1 work by Ashley + Eric together

= 1/77/1476

= 1 × 1476/77 = 1476/77 days

= 19 13/77 days = or 19.169 days

Thus, Ashley and Eric working together will finish the work in 19 13/77 days = or 19.169 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Ashley = 36 days

And the number of days required to finish the same work by Eric = 41 days

Thus, the number of days required to finish the work Ashley and Eric working together = ?

Here a = 36 days

And, b = 41 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Ashley and Eric working together

= 36 × 41/36 + 41 days

= 1476/77 days

= 19 13/77 days or 19.169

Thus, Ashley and Eric together will finish the work in 19 13/77 days or 19.169 days Answer


Similar Questions

(1) Christopher can finish a work in 21 days. Daniel can finish the same work in 22 days while Matthew can finish the work in 23 days. How long will it take to finish it if they work together?

(2) If Jennifer can finish the work in 29 days and Joseph can finish the same work in 45 days, then in how many days both can finish the work together?

(3) If Ashley can finish the work in 36 days and Eric can finish the same work in 41 days, then in how many days both can finish the work together?

(4) If Joseph can finish the work in 16 days and Steven can finish the same work in 19 days, then in how many days both can finish the work together?

(5) If Linda can finish the work in 12 days and Charles can finish the same work in 17 days, then in how many days both can finish the work together?

(6) Amanda can finish a work in 44 days. Dorothy can finish the same work in 45 days while Melissa can finish the work in 46 days. How long will it take to finish it if they work together?

(7) If Karen can finish the work in 21 days and Kevin can finish the same work in 25 days, then in how many days both can finish the work together?

(8) Timothy can finish a work in 49 days. Ronald can finish the same work in 50 days while Edward can finish the work in 51 days. How long will it take to finish it if they work together?

(9) If George can finish the work in 48 days and Dennis can finish the same work in 52 days, then in how many days both can finish the work together?

(10) If David can finish the work in 32 days and Christopher can finish the same work in 48 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©