Time and Work
MCQs Math


Question:     If Ashley can finish the work in 36 days and Eric can finish the same work in 41 days, then in how many days both can finish the work together?


Correct Answer  19 13/77 days or 19.169 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Ashley = 36 days

And, the number of days to finish the same work by Eric = 41 days

Thus, the number of days to finish the work by Ashley and Eric together = ?

Here,

∵ In 36 days the work done by Ashley = 1

∴ In 1 day, the work done by Ashley = 1/36 part

Similarly,

∵ In 41 days the work done by Eric = 1

∴ In 1 day, the work done by Eric = 1/41 part

Now, in 1 day, the work done by Ashley and Eric together

= In 1 day work done by Ashley + In 1 day the work done by Eric

= 1/36 + 1/41

= 41 + 36/1476

= 77/1476 part of work

This means in 1 day, 77/1476 part of work is done by Ashley and Eric working together.

Now, the number of days required to finish 77/1476 part of work by Ashley + Eric working together = 1

∴ the number of days required to finish 1 work by Ashley + Eric together

= 1/77/1476

= 1 × 1476/77 = 1476/77 days

= 19 13/77 days = or 19.169 days

Thus, Ashley and Eric working together will finish the work in 19 13/77 days = or 19.169 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Ashley = 36 days

And the number of days required to finish the same work by Eric = 41 days

Thus, the number of days required to finish the work Ashley and Eric working together = ?

Here a = 36 days

And, b = 41 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Ashley and Eric working together

= 36 × 41/36 + 41 days

= 1476/77 days

= 19 13/77 days or 19.169

Thus, Ashley and Eric together will finish the work in 19 13/77 days or 19.169 days Answer


Similar Questions

(1) If Scott can finish the work in 81 days and Bryan can finish the same work in 86 days, then in how many days both can finish the work together?

(2) If Kenneth can finish the work in 42 days and Gregory can finish the same work in 46 days, then in how many days both can finish the work together?

(3) If James can finish the work in 24 days and John can finish the same work in 40 days, then in how many days both can finish the work together?

(4) If Amy can finish the work in 68 days and Keith can finish the same work in 73 days, then in how many days both can finish the work together?

(5) If James can finish the work in 2 days and John can finish the same work in 5 days, then in how many days both can finish the work together?

(6) If Donna can finish the work in 39 days and Brandon can finish the same work in 42 days, then in how many days both can finish the work together?

(7) Joseph can finish a work in 15 days. Thomas can finish the same work in 16 days while Charles can finish the work in 17 days. How long will it take to finish it if they work together?

(8) If Nancy can finish the work in 25 days and Ronald can finish the same work in 28 days, then in how many days both can finish the work together?

(9) If William can finish the work in 12 days and Matthew can finish the same work in 15 days, then in how many days both can finish the work together?

(10) If Patricia can finish the work in 5 days and William can finish the same work in 8 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©