Time and Work
MCQs Math


Question:     If Paul can finish the work in 39 days and Larry can finish the same work in 44 days, then in how many days both can finish the work together?


Correct Answer  20 56/83 days or 20.675 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Paul = 39 days

And, the number of days to finish the same work by Larry = 44 days

Thus, the number of days to finish the work by Paul and Larry together = ?

Here,

∵ In 39 days the work done by Paul = 1

∴ In 1 day, the work done by Paul = 1/39 part

Similarly,

∵ In 44 days the work done by Larry = 1

∴ In 1 day, the work done by Larry = 1/44 part

Now, in 1 day, the work done by Paul and Larry together

= In 1 day work done by Paul + In 1 day the work done by Larry

= 1/39 + 1/44

= 44 + 39/1716

= 83/1716 part of work

This means in 1 day, 83/1716 part of work is done by Paul and Larry working together.

Now, the number of days required to finish 83/1716 part of work by Paul + Larry working together = 1

∴ the number of days required to finish 1 work by Paul + Larry together

= 1/83/1716

= 1 × 1716/83 = 1716/83 days

= 20 56/83 days = or 20.675 days

Thus, Paul and Larry working together will finish the work in 20 56/83 days = or 20.675 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Paul = 39 days

And the number of days required to finish the same work by Larry = 44 days

Thus, the number of days required to finish the work Paul and Larry working together = ?

Here a = 39 days

And, b = 44 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Paul and Larry working together

= 39 × 44/39 + 44 days

= 1716/83 days

= 20 56/83 days or 20.675

Thus, Paul and Larry together will finish the work in 20 56/83 days or 20.675 days Answer


Similar Questions

(1) If Raymond can finish the work in 97 days and Eugene can finish the same work in 102 days, then in how many days both can finish the work together?

(2) Joshua can finish a work in 39 days. Kenneth can finish the same work in 40 days while Kevin can finish the work in 41 days. How long will it take to finish it if they work together?

(3) Jennifer can finish a work in 6 days. Linda can finish the same work in 7 days while Elizabeth can finish the work in 8 days. How long will it take to finish it if they work together?

(4) George can finish a work in 51 days. Ronald can finish the same work in 56 days while Edward can finish the work in 61 days. How long will it take to finish it if they work together?

(5) If William can finish the work in 34 days and Matthew can finish the same work in 50 days, then in how many days both can finish the work together?

(6) Kevin can finish a work in 47 days. George can finish the same work in 52 days while Timothy can finish the work in 57 days. How long will it take to finish it if they work together?

(7) If Michael can finish the work in 11 days and Thomas can finish the same work in 16 days, then in how many days both can finish the work together?

(8) If Daniel can finish the work in 24 days and Timothy can finish the same work in 28 days, then in how many days both can finish the work together?

(9) If Karen can finish the work in 21 days and Kevin can finish the same work in 24 days, then in how many days both can finish the work together?

(10) If Kevin can finish the work in 44 days and Frank can finish the same work in 48 days, then in how many days both can finish the work together?