Time and Work
MCQs Math


Question:     If Jack can finish the work in 20 days and Bill can finish the same work in 30 days, then in how many days they both can finish the work working together?


Correct Answer  12 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Jack = 20 days

And, the number of days to finish the same work by Bill = 30 days

Thus, the number of days to finish the work by Jack and Bill working together = ?

Here, ∵ In 20 days the work done by Jack = 1

∴ In 1 day, the work done by Jack = 1/20 part

Similarly, ∵ In 30 days the work done by Bill = 1

∴ In 1 day, the work done by Bill = 1/30 part

Now, in 1 day, the work done by Jack and Bill working together

= In 1 day work done by Jack + In 1 day the work done by Bill

= 1/20 + 1/30

= 3 + 2/60

= 5 1/60 12 = 1/12 part of work

This means in 1 day, 1/12 part of work is done by Jack and Bill working together.

Now, the number of days required to finish 1/12 parts of work by Jack + Bill working together = 1

∴ the number of days required to finish 1 work by Robert + Bob working together

= 1/1/12

= 1 × 12/1 days = 12 days

Thus, Jack and Bill working together will finish the work in 12 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in "a" days, and B can finish the same work in "b" days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days to finish the work by Jack = 20 days

And, the number of days to finish the same work by Bill = 30 days

Thus, the number of days to finish the work by Jack and Bill working together = ?

Here "a" = 20 days

And, "b" = 30 days

Thus, using formula a × b/a + b days

The number of days require to finish the work when Jack and Bill working together

= 20 × 30/20 + 30

= 600 12/50 = 12 days

Thus, Jack and Bill working together will finish the work in 12 days Answer


Similar Questions

(1) If Robert can finish the work in 26 days and David can finish the same work in 42 days, then in how many days both can finish the work together?

(2) Gary can finish a work in 67 days. Eric can finish the same work in 72 days while Jonathan can finish the work in 77 days. How long will it take to finish it if they work together?

(3) If Michelle can finish the work in 41 days and Samuel can finish the same work in 44 days, then in how many days both can finish the work together?

(4) If Emily can finish the work in 37 days and Justin can finish the same work in 40 days, then in how many days both can finish the work together?

(5) Steven can finish a work in 37 days. Andrew can finish the same work in 42 days while Joshua can finish the work in 47 days. How long will it take to finish it if they work together?

(6) Catherine can finish a work in 100 days. Heather can finish the same work in 105 days while Diane can finish the work in 110 days. How long will it take to finish it if they work together?

(7) If Joshua can finish the work in 40 days and Benjamin can finish the same work in 43 days, then in how many days both can finish the work together?

(8) If Richard can finish the work in 36 days and Mark can finish the same work in 52 days, then in how many days both can finish the work together?

(9) Matthew can finish a work in 25 days. Anthony can finish the same work in 26 days while Mark can finish the work in 27 days. How long will it take to finish it if they work together?

(10) Gregory can finish a work in 89 days. Frank can finish the same work in 94 days while Patrick can finish the work in 99 days. How long will it take to finish it if they work together?