Time and Work
MCQs Math


Question:     If Nicholas can finish the work in 69 days and Roger can finish the same work in 74 days, then in how many days both can finish the work together?


Correct Answer  35 101/143 days or 35.706 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Nicholas = 69 days

And, the number of days to finish the same work by Roger = 74 days

Thus, the number of days to finish the work by Nicholas and Roger together = ?

Here,

∵ In 69 days the work done by Nicholas = 1

∴ In 1 day, the work done by Nicholas = 1/69 part

Similarly,

∵ In 74 days the work done by Roger = 1

∴ In 1 day, the work done by Roger = 1/74 part

Now, in 1 day, the work done by Nicholas and Roger together

= In 1 day work done by Nicholas + In 1 day the work done by Roger

= 1/69 + 1/74

= 74 + 69/5106

= 143/5106 part of work

This means in 1 day, 143/5106 part of work is done by Nicholas and Roger working together.

Now, the number of days required to finish 143/5106 part of work by Nicholas + Roger working together = 1

∴ the number of days required to finish 1 work by Nicholas + Roger together

= 1/143/5106

= 1 × 5106/143 = 5106/143 days

= 35 101/143 days = or 35.706 days

Thus, Nicholas and Roger working together will finish the work in 35 101/143 days = or 35.706 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Nicholas = 69 days

And the number of days required to finish the same work by Roger = 74 days

Thus, the number of days required to finish the work Nicholas and Roger working together = ?

Here a = 69 days

And, b = 74 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Nicholas and Roger working together

= 69 × 74/69 + 74 days

= 5106/143 days

= 35 101/143 days or 35.706

Thus, Nicholas and Roger together will finish the work in 35 101/143 days or 35.706 days Answer


Similar Questions

(1) David can finish a work in 9 days. William can finish the same work in 10 days while Richard can finish the work in 11 days. How long will it take to finish it if they work together?

(2) John can finish a work in 5 days. Michael can finish the same work in 6 days while David can finish the work in 7 days. How long will it take to finish it if they work together?

(3) If Pamela can finish the work in 78 days and Dylan can finish the same work in 83 days, then in how many days both can finish the work together?

(4) If Annie can finish a work in 6 days and Bobby can finish the same work in 12 days, then in how many days they both can finish the work working together?

(5) If Dorothy can finish the work in 47 days and Jack can finish the same work in 51 days, then in how many days both can finish the work together?

(6) Larry can finish a work in 77 days. Scott can finish the same work in 82 days while Brandon can finish the work in 87 days. How long will it take to finish it if they work together?

(7) If George can finish the work in 48 days and Dennis can finish the same work in 52 days, then in how many days both can finish the work together?

(8) If Daniel can finish the work in 24 days and Timothy can finish the same work in 28 days, then in how many days both can finish the work together?

(9) Susan can finish a work in 14 days. Jessica can finish the same work in 15 days while Sarah can finish the work in 16 days. How long will it take to finish it if they work together?

(10) Robert can finish a work in 7 days. Michael can finish the same work in 12 days while David can finish the work in 17 days. How long will it take to finish it if they work together?