Time and Work
MCQs Math


Question:     If Nicholas can finish the work in 69 days and Roger can finish the same work in 74 days, then in how many days both can finish the work together?


Correct Answer  35 101/143 days or 35.706 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Nicholas = 69 days

And, the number of days to finish the same work by Roger = 74 days

Thus, the number of days to finish the work by Nicholas and Roger together = ?

Here,

∵ In 69 days the work done by Nicholas = 1

∴ In 1 day, the work done by Nicholas = 1/69 part

Similarly,

∵ In 74 days the work done by Roger = 1

∴ In 1 day, the work done by Roger = 1/74 part

Now, in 1 day, the work done by Nicholas and Roger together

= In 1 day work done by Nicholas + In 1 day the work done by Roger

= 1/69 + 1/74

= 74 + 69/5106

= 143/5106 part of work

This means in 1 day, 143/5106 part of work is done by Nicholas and Roger working together.

Now, the number of days required to finish 143/5106 part of work by Nicholas + Roger working together = 1

∴ the number of days required to finish 1 work by Nicholas + Roger together

= 1/143/5106

= 1 × 5106/143 = 5106/143 days

= 35 101/143 days = or 35.706 days

Thus, Nicholas and Roger working together will finish the work in 35 101/143 days = or 35.706 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Nicholas = 69 days

And the number of days required to finish the same work by Roger = 74 days

Thus, the number of days required to finish the work Nicholas and Roger working together = ?

Here a = 69 days

And, b = 74 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Nicholas and Roger working together

= 69 × 74/69 + 74 days

= 5106/143 days

= 35 101/143 days or 35.706

Thus, Nicholas and Roger together will finish the work in 35 101/143 days or 35.706 days Answer


Similar Questions

(1) Thomas can finish a work in 17 days. Charles can finish the same work in 18 days while Christopher can finish the work in 19 days. How long will it take to finish it if they work together?

(2) If Margaret can finish the work in 29 days and Ryan can finish the same work in 33 days, then in how many days both can finish the work together?

(3) Brian can finish a work in 45 days. George can finish the same work in 46 days while Timothy can finish the work in 47 days. How long will it take to finish it if they work together?

(4) If Donald can finish the work in 32 days and Nicholas can finish the same work in 36 days, then in how many days both can finish the work together?

(5) If Karen can finish the work in 21 days and Kevin can finish the same work in 24 days, then in how many days both can finish the work together?

(6) Mary can finish a work in 6 days. Jennifer can finish the same work in 11 days while Linda can finish the work in 16 days. How long will it take to finish it if they work together?

(7) Joshua can finish a work in 43 days. Kevin can finish the same work in 48 days while Brian can finish the work in 53 days. How long will it take to finish it if they work together?

(8) If Michael can finish the work in 11 days and Thomas can finish the same work in 16 days, then in how many days both can finish the work together?

(9) If Brenda can finish the work in 76 days and Arthur can finish the same work in 81 days, then in how many days both can finish the work together?

(10) David can finish a work in 9 days. William can finish the same work in 10 days while Richard can finish the work in 11 days. How long will it take to finish it if they work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©