Time and Work
MCQs Math


Question:     If Stephen can finish the work in 75 days and Carl can finish the same work in 80 days, then in how many days both can finish the work together?


Correct Answer  38 22/31 days or 38.71 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Stephen = 75 days

And, the number of days to finish the same work by Carl = 80 days

Thus, the number of days to finish the work by Stephen and Carl together = ?

Here,

∵ In 75 days the work done by Stephen = 1

∴ In 1 day, the work done by Stephen = 1/75 part

Similarly,

∵ In 80 days the work done by Carl = 1

∴ In 1 day, the work done by Carl = 1/80 part

Now, in 1 day, the work done by Stephen and Carl together

= In 1 day work done by Stephen + In 1 day the work done by Carl

= 1/75 + 1/80

= 16 + 15/1200

= 31/1200 part of work

This means in 1 day, 31/1200 part of work is done by Stephen and Carl working together.

Now, the number of days required to finish 31/1200 part of work by Stephen + Carl working together = 1

∴ the number of days required to finish 1 work by Stephen + Carl together

= 1/31/1200

= 1 × 1200/31 = 1200/31 days

= 38 22/31 days = or 38.71 days

Thus, Stephen and Carl working together will finish the work in 38 22/31 days = or 38.71 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Stephen = 75 days

And the number of days required to finish the same work by Carl = 80 days

Thus, the number of days required to finish the work Stephen and Carl working together = ?

Here a = 75 days

And, b = 80 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Stephen and Carl working together

= 75 × 80/75 + 80 days

= 6000/155 days

= 6000 ÷ 5/155 ÷ 5 = 1200/31 days

= 38 22/31 days or 38.71

Thus, Stephen and Carl together will finish the work in 38 22/31 days or 38.71 days Answer


Similar Questions

(1) Jack can finish a work in 99 days. Jerry can finish the same work in 104 days while Tyler can finish the work in 109 days. How long will it take to finish it if they work together?

(2) If George can finish the work in 48 days and Dennis can finish the same work in 52 days, then in how many days both can finish the work together?

(3) Michael can finish a work in 7 days. David can finish the same work in 8 days while William can finish the work in 9 days. How long will it take to finish it if they work together?

(4) If Scott can finish the work in 81 days and Bryan can finish the same work in 86 days, then in how many days both can finish the work together?

(5) If Ashley can finish the work in 33 days and Eric can finish the same work in 36 days, then in how many days both can finish the work together?

(6) Samantha can finish a work in 86 days. Christine can finish the same work in 91 days while Debra can finish the work in 96 days. How long will it take to finish it if they work together?

(7) If Linda can finish the work in 9 days and Charles can finish the same work in 13 days, then in how many days both can finish the work together?

(8) Melissa can finish a work in 48 days. Deborah can finish the same work in 49 days while Stephanie can finish the work in 50 days. How long will it take to finish it if they work together?

(9) If Kimberly can finish the work in 35 days and Stephen can finish the same work in 38 days, then in how many days both can finish the work together?

(10) If Anthony can finish the work in 31 days and Jeffrey can finish the same work in 36 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©