Time and Work
MCQs Math


Question:     If A can do a piece of work in 2 days, B can do the same piece of work in 3 days, while C alone can do the same work in 4 days. Find the number of days to finish the work when they all will work together.


Correct Answer  12/13 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by A = 2

And, the number of days to finish the work by B = 3

And, the number of days to finish the work by C = 4

Thus, the number of days require to finish the work by working A, B, and C together = ?

Since in 2 days, A alone can finish the work.

∴ In 1 day work done by A = 1/2 part

Similarly,

Since in 3 days, B alone can finish the work.

∴ In 1 day work done by B = 1/3 part

Similarly,

Since in 4 days, C alone can finish the work.

∴ In 1 day work done by C = 1/4 part

Now, work done in 1 day by A, B and C working together

= A's 1 day work + B's 1 day work + C's 1 day work

= 1/2 + 1/3 + 1/4

= 6 + 4 + 3/12

⇒ Work done in 1 day by A, B, and C together = 13/12

Now, ∵ Number of days required to finish 13/12 part work by A, B, and C together = 1

∴ Number of days required to finish 1 work by A, B, and C together = 1/13/12

= 1 × 12/13 days

= 12/13 days

Thus, by working together A, B, C will finish the work in 12/13 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case (1): If A can finish a work in "a" days, and B can finish the same work in "b" days,
then working together the number of days require to finish the work
= a × b/a + b days.

Case (2): If A can finish a work in "a" days, and B can finish the same work in "b" days, and C can finish the work in "c" days,
then working together the number of days require to finish the work
= a × b × c/ab + bc + ac days.

Here given,

The number of days to finish the work by A = 2 days

And, the number of days to finish the same work by B = 3 days

And, the number of days to finish the same work by C = 4 days

Thus, the number of days to finish the work by A, B, and C together = ?

Here "a" = 2 days

And, "b" = 3 days

And, "c" = 4 days

Thus, using formula a × b × c/ab + bc + ac days

The number of days require to finish the work when A, B, and C together

= 2 × 3 × 4/(2 ×3) + (3 × 4) + (2 × 4) days

= 24/6 + 12 + 8 days

= 24/26 days

= 24 12/26 13 days

= 12/13 days

Thus, by working together A, B, C will finish the work in 12/13 days Answer


Similar Questions

(1) John can finish a work in 5 days. Michael can finish the same work in 6 days while David can finish the work in 7 days. How long will it take to finish it if they work together?

(2) Michelle can finish a work in 40 days. Carol can finish the same work in 41 days while Amanda can finish the work in 42 days. How long will it take to finish it if they work together?

(3) Deborah can finish a work in 50 days. Stephanie can finish the same work in 51 days while Rebecca can finish the work in 52 days. How long will it take to finish it if they work together?

(4) Brandon can finish a work in 83 days. Samuel can finish the same work in 88 days while Gregory can finish the work in 93 days. How long will it take to finish it if they work together?

(5) If Matthew can finish the work in 29 days and Edward can finish the same work in 34 days, then in how many days both can finish the work together?

(6) If Dorothy can finish the work in 47 days and Jack can finish the same work in 51 days, then in how many days both can finish the work together?

(7) Nancy can finish a work in 24 days. Betty can finish the same work in 25 days while Margaret can finish the work in 26 days. How long will it take to finish it if they work together?

(8) If Amy can finish the work in 68 days and Keith can finish the same work in 73 days, then in how many days both can finish the work together?

(9) If Brenda can finish the work in 76 days and Arthur can finish the same work in 81 days, then in how many days both can finish the work together?

(10) If Timothy can finish the work in 53 days and Tyler can finish the same work in 58 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©