Time and Work
MCQs Math


Question:     If Samuel can finish the work in 87 days and Albert can finish the same work in 92 days, then in how many days both can finish the work together?


Correct Answer  44 128/179 days or 44.715 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Samuel = 87 days

And, the number of days to finish the same work by Albert = 92 days

Thus, the number of days to finish the work by Samuel and Albert together = ?

Here,

∵ In 87 days the work done by Samuel = 1

∴ In 1 day, the work done by Samuel = 1/87 part

Similarly,

∵ In 92 days the work done by Albert = 1

∴ In 1 day, the work done by Albert = 1/92 part

Now, in 1 day, the work done by Samuel and Albert together

= In 1 day work done by Samuel + In 1 day the work done by Albert

= 1/87 + 1/92

= 92 + 87/8004

= 179/8004 part of work

This means in 1 day, 179/8004 part of work is done by Samuel and Albert working together.

Now, the number of days required to finish 179/8004 part of work by Samuel + Albert working together = 1

∴ the number of days required to finish 1 work by Samuel + Albert together

= 1/179/8004

= 1 × 8004/179 = 8004/179 days

= 44 128/179 days = or 44.715 days

Thus, Samuel and Albert working together will finish the work in 44 128/179 days = or 44.715 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Samuel = 87 days

And the number of days required to finish the same work by Albert = 92 days

Thus, the number of days required to finish the work Samuel and Albert working together = ?

Here a = 87 days

And, b = 92 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Samuel and Albert working together

= 87 × 92/87 + 92 days

= 8004/179 days

= 44 128/179 days or 44.715

Thus, Samuel and Albert together will finish the work in 44 128/179 days or 44.715 days Answer


Similar Questions

(1) If Kevin can finish the work in 44 days and Frank can finish the same work in 47 days, then in how many days both can finish the work together?

(2) If Carol can finish the work in 43 days and Alexander can finish the same work in 47 days, then in how many days both can finish the work together?

(3) If Patricia can finish the work in 8 days and William can finish the same work in 13 days, then in how many days both can finish the work together?

(4) Jessica can finish a work in 16 days. Sarah can finish the same work in 17 days while Karen can finish the work in 18 days. How long will it take to finish it if they work together?

(5) If Carol can finish the work in 46 days and Alexander can finish the same work in 51 days, then in how many days both can finish the work together?

(6) If Sarah can finish the work in 19 days and Joshua can finish the same work in 23 days, then in how many days both can finish the work together?

(7) If Brian can finish the work in 46 days and Raymond can finish the same work in 50 days, then in how many days both can finish the work together?

(8) Carol can finish a work in 46 days. Dorothy can finish the same work in 51 days while Melissa can finish the work in 56 days. How long will it take to finish it if they work together?

(9) If Emily can finish the work in 37 days and Justin can finish the same work in 41 days, then in how many days both can finish the work together?

(10) Donald can finish a work in 35 days. Paul can finish the same work in 40 days while Andrew can finish the work in 45 days. How long will it take to finish it if they work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©