Time and Work
MCQs Math


Question:     If Katherine can finish the work in 88 days and Willie can finish the same work in 93 days, then in how many days both can finish the work together?


Correct Answer  45 39/181 days or 45.215 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Katherine = 88 days

And, the number of days to finish the same work by Willie = 93 days

Thus, the number of days to finish the work by Katherine and Willie together = ?

Here,

∵ In 88 days the work done by Katherine = 1

∴ In 1 day, the work done by Katherine = 1/88 part

Similarly,

∵ In 93 days the work done by Willie = 1

∴ In 1 day, the work done by Willie = 1/93 part

Now, in 1 day, the work done by Katherine and Willie together

= In 1 day work done by Katherine + In 1 day the work done by Willie

= 1/88 + 1/93

= 93 + 88/8184

= 181/8184 part of work

This means in 1 day, 181/8184 part of work is done by Katherine and Willie working together.

Now, the number of days required to finish 181/8184 part of work by Katherine + Willie working together = 1

∴ the number of days required to finish 1 work by Katherine + Willie together

= 1/181/8184

= 1 × 8184/181 = 8184/181 days

= 45 39/181 days = or 45.215 days

Thus, Katherine and Willie working together will finish the work in 45 39/181 days = or 45.215 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Katherine = 88 days

And the number of days required to finish the same work by Willie = 93 days

Thus, the number of days required to finish the work Katherine and Willie working together = ?

Here a = 88 days

And, b = 93 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Katherine and Willie working together

= 88 × 93/88 + 93 days

= 8184/181 days

= 45 39/181 days or 45.215

Thus, Katherine and Willie together will finish the work in 45 39/181 days or 45.215 days Answer


Similar Questions

(1) If Andrew can finish the work in 38 days and Scott can finish the same work in 41 days, then in how many days both can finish the work together?

(2) If Jack can finish the work in 99 days and Bobby can finish the same work in 104 days, then in how many days both can finish the work together?

(3) If Steven can finish the work in 34 days and Jonathan can finish the same work in 37 days, then in how many days both can finish the work together?

(4) If Elizabeth can finish the work in 33 days and Daniel can finish the same work in 49 days, then in how many days both can finish the work together?

(5) William can finish a work in 11 days. Richard can finish the same work in 12 days while Joseph can finish the work in 13 days. How long will it take to finish it if they work together?

(6) If Michael can finish the work in 30 days and Thomas can finish the same work in 46 days, then in how many days both can finish the work together?

(7) Frank can finish a work in 93 days. Raymond can finish the same work in 98 days while Jack can finish the work in 103 days. How long will it take to finish it if they work together?

(8) If Linda can finish the work in 9 days and Charles can finish the same work in 13 days, then in how many days both can finish the work together?

(9) If Nancy can finish the work in 25 days and Ronald can finish the same work in 28 days, then in how many days both can finish the work together?

(10) If Sarah can finish the work in 19 days and Joshua can finish the same work in 22 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©