Time and Work
MCQs Math


Question:     If Alexander can finish the work in 91 days and Wayne can finish the same work in 96 days, then in how many days both can finish the work together?


Correct Answer  46 134/187 days or 46.717 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Alexander = 91 days

And, the number of days to finish the same work by Wayne = 96 days

Thus, the number of days to finish the work by Alexander and Wayne together = ?

Here,

∵ In 91 days the work done by Alexander = 1

∴ In 1 day, the work done by Alexander = 1/91 part

Similarly,

∵ In 96 days the work done by Wayne = 1

∴ In 1 day, the work done by Wayne = 1/96 part

Now, in 1 day, the work done by Alexander and Wayne together

= In 1 day work done by Alexander + In 1 day the work done by Wayne

= 1/91 + 1/96

= 96 + 91/8736

= 187/8736 part of work

This means in 1 day, 187/8736 part of work is done by Alexander and Wayne working together.

Now, the number of days required to finish 187/8736 part of work by Alexander + Wayne working together = 1

∴ the number of days required to finish 1 work by Alexander + Wayne together

= 1/187/8736

= 1 × 8736/187 = 8736/187 days

= 46 134/187 days = or 46.717 days

Thus, Alexander and Wayne working together will finish the work in 46 134/187 days = or 46.717 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Alexander = 91 days

And the number of days required to finish the same work by Wayne = 96 days

Thus, the number of days required to finish the work Alexander and Wayne working together = ?

Here a = 91 days

And, b = 96 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Alexander and Wayne working together

= 91 × 96/91 + 96 days

= 8736/187 days

= 46 134/187 days or 46.717

Thus, Alexander and Wayne together will finish the work in 46 134/187 days or 46.717 days Answer


Similar Questions

(1) If Amanda can finish the work in 45 days and Patrick can finish the same work in 48 days, then in how many days both can finish the work together?

(2) If Betty can finish the work in 27 days and Jason can finish the same work in 31 days, then in how many days both can finish the work together?

(3) If Joshua can finish the work in 40 days and Benjamin can finish the same work in 43 days, then in how many days both can finish the work together?

(4) Stephanie can finish a work in 56 days. Sharon can finish the same work in 61 days while Laura can finish the work in 66 days. How long will it take to finish it if they work together?

(5) If Mark can finish the work in 30 days and Jacob can finish the same work in 33 days, then in how many days both can finish the work together?

(6) If Rachel can finish the work in 94 days and Roy can finish the same work in 99 days, then in how many days both can finish the work together?

(7) If Patrick can finish the work in 95 days and Vincent can finish the same work in 100 days, then in how many days both can finish the work together?

(8) If Edward can finish the work in 57 days and Nathan can finish the same work in 62 days, then in how many days both can finish the work together?

(9) If Steven can finish the work in 37 days and Jonathan can finish the same work in 42 days, then in how many days both can finish the work together?

(10) If Dorothy can finish the work in 47 days and Jack can finish the same work in 51 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©