Question:     If Rachel can finish the work in 94 days and Roy can finish the same work in 99 days, then in how many days both can finish the work together?


Correct Answer  48 42/193 days or 48.218 days

Solution And Explanation

Solution

Given,

The number of days to finish the work by Rachel = 94 days

And, the number of days to finish the same work by Roy = 99 days

Thus, the number of days to finish the work by Rachel and Roy together = ?

Here,

∵ In 94 days the work done by Rachel = 1

∴ In 1 day, the work done by Rachel = 1/94 part

Similarly,

∵ In 99 days the work done by Roy = 1

∴ In 1 day, the work done by Roy = 1/99 part

Now, in 1 day, the work done by Rachel and Roy together

= In 1 day work done by Rachel + In 1 day the work done by Roy

= 1/94 + 1/99

= 99 + 94/9306

= 193/9306 part of work

This means in 1 day, 193/9306 part of work is done by Rachel and Roy working together.

Now, the number of days required to finish 193/9306 part of work by Rachel + Roy working together = 1

∴ the number of days required to finish 1 work by Rachel + Roy together

= 1/193/9306

= 1 × 9306/193 = 9306/193 days

= 48 42/193 days = or 48.218 days

Thus, Rachel and Roy working together will finish the work in 48 42/193 days = or 48.218 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, and B can finish the same work in b days,
then working together the number of days require to finish the work
= a × b/a + b days.

Here given,

The number of days required to finish the work by Rachel = 94 days

And the number of days required to finish the same work by Roy = 99 days

Thus, the number of days required to finish the work Rachel and Roy working together = ?

Here a = 94 days

And, b = 99 days

Thus, using formula a × b/a + b days

The number of days required to finish the work when Rachel and Roy working together

= 94 × 99/94 + 99 days

= 9306/193 days

= 48 42/193 days or 48.218

Thus, Rachel and Roy together will finish the work in 48 42/193 days or 48.218 days Answer


Similar Questions

(1) If Donna can finish the work in 42 days and Brandon can finish the same work in 47 days, then in how many days both can finish the work together?

(2) If Joshua can finish the work in 40 days and Benjamin can finish the same work in 43 days, then in how many days both can finish the work together?

(3) Joseph can finish a work in 15 days. Thomas can finish the same work in 16 days while Charles can finish the work in 17 days. How long will it take to finish it if they work together?

(4) If Amanda can finish the work in 45 days and Patrick can finish the same work in 49 days, then in how many days both can finish the work together?

(5) If Brandon can finish the work in 83 days and Joe can finish the same work in 88 days, then in how many days both can finish the work together?

(6) If Mary can finish the work in 25 days and Michael can finish the same work in 41 days, then in how many days both can finish the work together?

(7) George can finish a work in 47 days. Timothy can finish the same work in 48 days while Ronald can finish the work in 49 days. How long will it take to finish it if they work together?

(8) If Jessica can finish the work in 17 days and Paul can finish the same work in 20 days, then in how many days both can finish the work together?

(9) John can finish a work in 5 days. Michael can finish the same work in 6 days while David can finish the work in 7 days. How long will it take to finish it if they work together?

(10) If Mary can finish the work in 6 days and Michael can finish the same work in 11 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©