Time and Work
MCQs Math


Question:     James can finish a work in 5 days. John can finish the same work in 10 days while Michael can finish the work in 15 days. How long will it take to finish it if they work together?


Correct Answer  2 8/11 days or 2.727 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by James = 5 days

And, the number of days required to finish the same work by John = 10 days

And, the number of days required to finish the same work by Michael = 15 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 5 days the work is done by James = 1

∴ The work done by James in 1 day = 1/5

Similarly,

∵ In 10 days the work is done by John = 1

∴ The work done by John in 1 day = 1/10

Similarly,

∵ In 15 days the work is done by Michael = 1

∴ The work done by Michael in 1 day = 1/15 part

Now, the work done by James, John, and Michael together in 1 day

= James's 1 day work + John's 1 day work + Michael's 1 day work

= 1/5 + 1/10 + 1/15

= 6 + 3 + 2/30

= 11/30 part of work

This means in 1 day, 11/30 part of work is done by James, John and Michael working together.

Now, the number of days required to finish 11/30 part of work by James, John, and Michael working together = 1

∴ the number of days required to finish the whole work (1 work) by James + John + Michael together

= 1/11/30

= 1 × 30/11 = 30/11 days

= 2 8/11 days = or 2.727 days

Thus, James, John, and Michael working together will finish the total work (1 work) in 2 8/11 days = or 2.727 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by James = 5 days

And the number of days required to finish the same work by John = 10 days

And the number of days required to finish the work by Michael = 15 days

Thus, the number of days required to finish the work by James, John, and Michael together = ?

Here a = 5 days

And, b = 10 days

And, c = 15 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when James, John, and Michael working together

= 5 × 10 × 15/5 × 10 + 5 × 15 + 10 × 15 days

= 750/50 + 75 + 150 days

= 750/275 days

= 750/275 days

= 750 ÷ 25/275 ÷ 25 = 30/11 days

= 2 8/11 days or 2.727

Thus, James, John, and Michael together will finish the work in 2 8/11 days or 2.727 days Answer


Similar Questions

(1) Barbara can finish a work in 16 days. Jessica can finish the same work in 21 days while Sarah can finish the work in 26 days. How long will it take to finish it if they work together?

(2) Katherine can finish a work in 88 days. Debra can finish the same work in 93 days while Rachel can finish the work in 98 days. How long will it take to finish it if they work together?

(3) George can finish a work in 47 days. Timothy can finish the same work in 48 days while Ronald can finish the work in 49 days. How long will it take to finish it if they work together?

(4) If Raymond can finish the work in 97 days and Eugene can finish the same work in 102 days, then in how many days both can finish the work together?

(5) John can finish a work in 5 days. Michael can finish the same work in 6 days while David can finish the work in 7 days. How long will it take to finish it if they work together?

(6) If Scott can finish the work in 81 days and Bryan can finish the same work in 86 days, then in how many days both can finish the work together?

(7) If Paul can finish the work in 36 days and Larry can finish the same work in 39 days, then in how many days both can finish the work together?

(8) Nancy can finish a work in 28 days. Margaret can finish the same work in 33 days while Sandra can finish the work in 38 days. How long will it take to finish it if they work together?

(9) If Robert can finish the work in 4 days and David can finish the same work in 8 days, then in how many days both can finish the work together?

(10) If Linda can finish the work in 9 days and Charles can finish the same work in 13 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©