Time and Work
MCQs Math


Question:     John can finish a work in 9 days. David can finish the same work in 14 days while William can finish the work in 19 days. How long will it take to finish it if they work together?


Correct Answer  4 142/563 days or 4.252 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by John = 9 days

And, the number of days required to finish the same work by David = 14 days

And, the number of days required to finish the same work by William = 19 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 9 days the work is done by John = 1

∴ The work done by John in 1 day = 1/9

Similarly,

∵ In 14 days the work is done by David = 1

∴ The work done by David in 1 day = 1/14

Similarly,

∵ In 19 days the work is done by William = 1

∴ The work done by William in 1 day = 1/19 part

Now, the work done by John, David, and William together in 1 day

= John's 1 day work + David's 1 day work + William's 1 day work

= 1/9 + 1/14 + 1/19

= 266 + 171 + 126/2394

= 563/2394 part of work

This means in 1 day, 563/2394 part of work is done by John, David and William working together.

Now, the number of days required to finish 563/2394 part of work by John, David, and William working together = 1

∴ the number of days required to finish the whole work (1 work) by John + David + William together

= 1/563/2394

= 1 × 2394/563 = 2394/563 days

= 4 142/563 days = or 4.252 days

Thus, John, David, and William working together will finish the total work (1 work) in 4 142/563 days = or 4.252 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by John = 9 days

And the number of days required to finish the same work by David = 14 days

And the number of days required to finish the work by William = 19 days

Thus, the number of days required to finish the work by John, David, and William together = ?

Here a = 9 days

And, b = 14 days

And, c = 19 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when John, David, and William working together

= 9 × 14 × 19/9 × 14 + 9 × 19 + 14 × 19 days

= 2394/126 + 171 + 266 days

= 2394/563 days

= 2394/563 days

= 4 142/563 days or 4.252

Thus, John, David, and William together will finish the work in 4 142/563 days or 4.252 days Answer


Similar Questions

(1) Ashley can finish a work in 32 days. Kimberly can finish the same work in 33 days while Emily can finish the work in 34 days. How long will it take to finish it if they work together?

(2) Betty can finish a work in 30 days. Sandra can finish the same work in 35 days while Ashley can finish the work in 40 days. How long will it take to finish it if they work together?

(3) If Jack can finish the work in 99 days and Bobby can finish the same work in 104 days, then in how many days both can finish the work together?

(4) If Linda can finish the work in 9 days and Charles can finish the same work in 13 days, then in how many days both can finish the work together?

(5) If Matthew can finish the work in 26 days and Edward can finish the same work in 30 days, then in how many days both can finish the work together?

(6) John can finish a work in 5 days. Michael can finish the same work in 6 days while David can finish the work in 7 days. How long will it take to finish it if they work together?

(7) Joshua can finish a work in 39 days. Kenneth can finish the same work in 40 days while Kevin can finish the work in 41 days. How long will it take to finish it if they work together?

(8) If Anthony can finish the work in 28 days and Jeffrey can finish the same work in 32 days, then in how many days both can finish the work together?

(9) If John can finish the work in 28 days and Richard can finish the same work in 44 days, then in how many days both can finish the work together?

(10) Amanda can finish a work in 44 days. Dorothy can finish the same work in 45 days while Melissa can finish the work in 46 days. How long will it take to finish it if they work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©