Time and Work
MCQs Math


Question:     William can finish a work in 15 days. Joseph can finish the same work in 20 days while Thomas can finish the work in 25 days. How long will it take to finish it if they work together?


Correct Answer  6 18/47 days or 6.383 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by William = 15 days

And, the number of days required to finish the same work by Joseph = 20 days

And, the number of days required to finish the same work by Thomas = 25 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 15 days the work is done by William = 1

∴ The work done by William in 1 day = 1/15

Similarly,

∵ In 20 days the work is done by Joseph = 1

∴ The work done by Joseph in 1 day = 1/20

Similarly,

∵ In 25 days the work is done by Thomas = 1

∴ The work done by Thomas in 1 day = 1/25 part

Now, the work done by William, Joseph, and Thomas together in 1 day

= William's 1 day work + Joseph's 1 day work + Thomas's 1 day work

= 1/15 + 1/20 + 1/25

= 20 + 15 + 12/300

= 47/300 part of work

This means in 1 day, 47/300 part of work is done by William, Joseph and Thomas working together.

Now, the number of days required to finish 47/300 part of work by William, Joseph, and Thomas working together = 1

∴ the number of days required to finish the whole work (1 work) by William + Joseph + Thomas together

= 1/47/300

= 1 × 300/47 = 300/47 days

= 6 18/47 days = or 6.383 days

Thus, William, Joseph, and Thomas working together will finish the total work (1 work) in 6 18/47 days = or 6.383 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by William = 15 days

And the number of days required to finish the same work by Joseph = 20 days

And the number of days required to finish the work by Thomas = 25 days

Thus, the number of days required to finish the work by William, Joseph, and Thomas together = ?

Here a = 15 days

And, b = 20 days

And, c = 25 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when William, Joseph, and Thomas working together

= 15 × 20 × 25/15 × 20 + 15 × 25 + 20 × 25 days

= 7500/300 + 375 + 500 days

= 7500/1175 days

= 7500/1175 days

= 7500 ÷ 25/1175 ÷ 25 = 300/47 days

= 6 18/47 days or 6.383

Thus, William, Joseph, and Thomas together will finish the work in 6 18/47 days or 6.383 days Answer


Similar Questions

(1) Jonathan can finish a work in 73 days. Larry can finish the same work in 78 days while Justin can finish the work in 83 days. How long will it take to finish it if they work together?

(2) If Margaret can finish the work in 29 days and Ryan can finish the same work in 32 days, then in how many days both can finish the work together?

(3) Linda can finish a work in 8 days. Elizabeth can finish the same work in 9 days while Barbara can finish the work in 10 days. How long will it take to finish it if they work together?

(4) If Michael can finish the work in 8 days and Thomas can finish the same work in 11 days, then in how many days both can finish the work together?

(5) If Steven can finish the work in 34 days and Jonathan can finish the same work in 38 days, then in how many days both can finish the work together?

(6) If Janet can finish the work in 98 days and Russell can finish the same work in 103 days, then in how many days both can finish the work together?

(7) Lisa can finish a work in 22 days. Nancy can finish the same work in 23 days while Betty can finish the work in 24 days. How long will it take to finish it if they work together?

(8) If David can finish the work in 10 days and Christopher can finish the same work in 14 days, then in how many days both can finish the work together?

(9) If Shirley can finish the work in 72 days and Harold can finish the same work in 77 days, then in how many days both can finish the work together?

(10) If Michael can finish the work in 30 days and Thomas can finish the same work in 46 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©