Time and Work
MCQs Math


Question:     Karen can finish a work in 24 days. Nancy can finish the same work in 29 days while Betty can finish the work in 34 days. How long will it take to finish it if they work together?


Correct Answer  9 591/1249 days or 9.473 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Karen = 24 days

And, the number of days required to finish the same work by Nancy = 29 days

And, the number of days required to finish the same work by Betty = 34 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 24 days the work is done by Karen = 1

∴ The work done by Karen in 1 day = 1/24

Similarly,

∵ In 29 days the work is done by Nancy = 1

∴ The work done by Nancy in 1 day = 1/29

Similarly,

∵ In 34 days the work is done by Betty = 1

∴ The work done by Betty in 1 day = 1/34 part

Now, the work done by Karen, Nancy, and Betty together in 1 day

= Karen's 1 day work + Nancy's 1 day work + Betty's 1 day work

= 1/24 + 1/29 + 1/34

= 493 + 408 + 348/11832

= 1249/11832 part of work

This means in 1 day, 1249/11832 part of work is done by Karen, Nancy and Betty working together.

Now, the number of days required to finish 1249/11832 part of work by Karen, Nancy, and Betty working together = 1

∴ the number of days required to finish the whole work (1 work) by Karen + Nancy + Betty together

= 1/1249/11832

= 1 × 11832/1249 = 11832/1249 days

= 9 591/1249 days = or 9.473 days

Thus, Karen, Nancy, and Betty working together will finish the total work (1 work) in 9 591/1249 days = or 9.473 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Karen = 24 days

And the number of days required to finish the same work by Nancy = 29 days

And the number of days required to finish the work by Betty = 34 days

Thus, the number of days required to finish the work by Karen, Nancy, and Betty together = ?

Here a = 24 days

And, b = 29 days

And, c = 34 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Karen, Nancy, and Betty working together

= 24 × 29 × 34/24 × 29 + 24 × 34 + 29 × 34 days

= 23664/696 + 816 + 986 days

= 23664/2498 days

= 23664/2498 days

= 23664 ÷ 2/2498 ÷ 2 = 11832/1249 days

= 9 591/1249 days or 9.473

Thus, Karen, Nancy, and Betty together will finish the work in 9 591/1249 days or 9.473 days Answer


Similar Questions

(1) If Kevin can finish the work in 44 days and Frank can finish the same work in 48 days, then in how many days both can finish the work together?

(2) Paul can finish a work in 39 days. Joshua can finish the same work in 44 days while Kenneth can finish the work in 49 days. How long will it take to finish it if they work together?

(3) If Angela can finish the work in 70 days and Terry can finish the same work in 75 days, then in how many days both can finish the work together?

(4) Donna can finish a work in 38 days. Michelle can finish the same work in 39 days while Carol can finish the work in 40 days. How long will it take to finish it if they work together?

(5) If Cynthia can finish the work in 64 days and Walter can finish the same work in 69 days, then in how many days both can finish the work together?

(6) If Richard can finish the work in 14 days and Mark can finish the same work in 17 days, then in how many days both can finish the work together?

(7) Donald can finish a work in 35 days. Paul can finish the same work in 40 days while Andrew can finish the work in 45 days. How long will it take to finish it if they work together?

(8) If Carol can finish the work in 46 days and Alexander can finish the same work in 51 days, then in how many days both can finish the work together?

(9) Rebecca can finish a work in 58 days. Laura can finish the same work in 63 days while Cynthia can finish the work in 68 days. How long will it take to finish it if they work together?

(10) If Nancy can finish the work in 25 days and Ronald can finish the same work in 29 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©