Time and Work
MCQs Math


Question:     Lisa can finish a work in 26 days. Betty can finish the same work in 31 days while Margaret can finish the work in 36 days. How long will it take to finish it if they work together?


Correct Answer  10 218/1429 days or 10.153 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Lisa = 26 days

And, the number of days required to finish the same work by Betty = 31 days

And, the number of days required to finish the same work by Margaret = 36 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 26 days the work is done by Lisa = 1

∴ The work done by Lisa in 1 day = 1/26

Similarly,

∵ In 31 days the work is done by Betty = 1

∴ The work done by Betty in 1 day = 1/31

Similarly,

∵ In 36 days the work is done by Margaret = 1

∴ The work done by Margaret in 1 day = 1/36 part

Now, the work done by Lisa, Betty, and Margaret together in 1 day

= Lisa's 1 day work + Betty's 1 day work + Margaret's 1 day work

= 1/26 + 1/31 + 1/36

= 558 + 468 + 403/14508

= 1429/14508 part of work

This means in 1 day, 1429/14508 part of work is done by Lisa, Betty and Margaret working together.

Now, the number of days required to finish 1429/14508 part of work by Lisa, Betty, and Margaret working together = 1

∴ the number of days required to finish the whole work (1 work) by Lisa + Betty + Margaret together

= 1/1429/14508

= 1 × 14508/1429 = 14508/1429 days

= 10 218/1429 days = or 10.153 days

Thus, Lisa, Betty, and Margaret working together will finish the total work (1 work) in 10 218/1429 days = or 10.153 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Lisa = 26 days

And the number of days required to finish the same work by Betty = 31 days

And the number of days required to finish the work by Margaret = 36 days

Thus, the number of days required to finish the work by Lisa, Betty, and Margaret together = ?

Here a = 26 days

And, b = 31 days

And, c = 36 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Lisa, Betty, and Margaret working together

= 26 × 31 × 36/26 × 31 + 26 × 36 + 31 × 36 days

= 29016/806 + 936 + 1116 days

= 29016/2858 days

= 29016/2858 days

= 29016 ÷ 2/2858 ÷ 2 = 14508/1429 days

= 10 218/1429 days or 10.153

Thus, Lisa, Betty, and Margaret together will finish the work in 10 218/1429 days or 10.153 days Answer


Similar Questions

(1) If Anthony can finish the work in 28 days and Jeffrey can finish the same work in 31 days, then in how many days both can finish the work together?

(2) If Paul can finish the work in 36 days and Larry can finish the same work in 40 days, then in how many days both can finish the work together?

(3) Betty can finish a work in 30 days. Sandra can finish the same work in 35 days while Ashley can finish the work in 40 days. How long will it take to finish it if they work together?

(4) If Samuel can finish the work in 87 days and Albert can finish the same work in 92 days, then in how many days both can finish the work together?

(5) If Barbara can finish the work in 13 days and Anthony can finish the same work in 16 days, then in how many days both can finish the work together?

(6) If James can finish the work in 24 days and John can finish the same work in 40 days, then in how many days both can finish the work together?

(7) Christopher can finish a work in 25 days. Matthew can finish the same work in 30 days while Anthony can finish the work in 35 days. How long will it take to finish it if they work together?

(8) If Jennifer can finish the work in 7 days and Joseph can finish the same work in 11 days, then in how many days both can finish the work together?

(9) If Robert can finish the work in 4 days and David can finish the same work in 8 days, then in how many days both can finish the work together?

(10) Patrick can finish a work in 95 days. Jack can finish the same work in 100 days while Dennis can finish the work in 105 days. How long will it take to finish it if they work together?