Time and Work
MCQs Math


Question:     Daniel can finish a work in 27 days. Anthony can finish the same work in 32 days while Mark can finish the work in 37 days. How long will it take to finish it if they work together?


Correct Answer  10 1498/3047 days or 10.492 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Daniel = 27 days

And, the number of days required to finish the same work by Anthony = 32 days

And, the number of days required to finish the same work by Mark = 37 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 27 days the work is done by Daniel = 1

∴ The work done by Daniel in 1 day = 1/27

Similarly,

∵ In 32 days the work is done by Anthony = 1

∴ The work done by Anthony in 1 day = 1/32

Similarly,

∵ In 37 days the work is done by Mark = 1

∴ The work done by Mark in 1 day = 1/37 part

Now, the work done by Daniel, Anthony, and Mark together in 1 day

= Daniel's 1 day work + Anthony's 1 day work + Mark's 1 day work

= 1/27 + 1/32 + 1/37

= 1184 + 999 + 864/31968

= 3047/31968 part of work

This means in 1 day, 3047/31968 part of work is done by Daniel, Anthony and Mark working together.

Now, the number of days required to finish 3047/31968 part of work by Daniel, Anthony, and Mark working together = 1

∴ the number of days required to finish the whole work (1 work) by Daniel + Anthony + Mark together

= 1/3047/31968

= 1 × 31968/3047 = 31968/3047 days

= 10 1498/3047 days = or 10.492 days

Thus, Daniel, Anthony, and Mark working together will finish the total work (1 work) in 10 1498/3047 days = or 10.492 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Daniel = 27 days

And the number of days required to finish the same work by Anthony = 32 days

And the number of days required to finish the work by Mark = 37 days

Thus, the number of days required to finish the work by Daniel, Anthony, and Mark together = ?

Here a = 27 days

And, b = 32 days

And, c = 37 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Daniel, Anthony, and Mark working together

= 27 × 32 × 37/27 × 32 + 27 × 37 + 32 × 37 days

= 31968/864 + 999 + 1184 days

= 31968/3047 days

= 31968/3047 days

= 10 1498/3047 days or 10.492

Thus, Daniel, Anthony, and Mark together will finish the work in 10 1498/3047 days or 10.492 days Answer


Similar Questions

(1) Joshua can finish a work in 39 days. Kenneth can finish the same work in 40 days while Kevin can finish the work in 41 days. How long will it take to finish it if they work together?

(2) Jessica can finish a work in 20 days. Karen can finish the same work in 25 days while Lisa can finish the work in 30 days. How long will it take to finish it if they work together?

(3) Eric can finish a work in 71 days. Stephen can finish the same work in 76 days while Larry can finish the work in 81 days. How long will it take to finish it if they work together?

(4) If Dorothy can finish the work in 50 days and Jack can finish the same work in 55 days, then in how many days both can finish the work together?

(5) Paul can finish a work in 39 days. Joshua can finish the same work in 44 days while Kenneth can finish the work in 49 days. How long will it take to finish it if they work together?

(6) If Helen can finish the work in 84 days and Bruce can finish the same work in 89 days, then in how many days both can finish the work together?

(7) If Alexander can finish the work in 91 days and Wayne can finish the same work in 96 days, then in how many days both can finish the work together?

(8) If Edward can finish the work in 57 days and Nathan can finish the same work in 62 days, then in how many days both can finish the work together?

(9) If Donald can finish the work in 32 days and Nicholas can finish the same work in 36 days, then in how many days both can finish the work together?

(10) If James can finish the work in 2 days and John can finish the same work in 5 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©