Time and Work
MCQs Math


Question:     Nancy can finish a work in 28 days. Margaret can finish the same work in 33 days while Sandra can finish the work in 38 days. How long will it take to finish it if they work together?


Correct Answer  10 1346/1621 days or 10.83 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Nancy = 28 days

And, the number of days required to finish the same work by Margaret = 33 days

And, the number of days required to finish the same work by Sandra = 38 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 28 days the work is done by Nancy = 1

∴ The work done by Nancy in 1 day = 1/28

Similarly,

∵ In 33 days the work is done by Margaret = 1

∴ The work done by Margaret in 1 day = 1/33

Similarly,

∵ In 38 days the work is done by Sandra = 1

∴ The work done by Sandra in 1 day = 1/38 part

Now, the work done by Nancy, Margaret, and Sandra together in 1 day

= Nancy's 1 day work + Margaret's 1 day work + Sandra's 1 day work

= 1/28 + 1/33 + 1/38

= 627 + 532 + 462/17556

= 1621/17556 part of work

This means in 1 day, 1621/17556 part of work is done by Nancy, Margaret and Sandra working together.

Now, the number of days required to finish 1621/17556 part of work by Nancy, Margaret, and Sandra working together = 1

∴ the number of days required to finish the whole work (1 work) by Nancy + Margaret + Sandra together

= 1/1621/17556

= 1 × 17556/1621 = 17556/1621 days

= 10 1346/1621 days = or 10.83 days

Thus, Nancy, Margaret, and Sandra working together will finish the total work (1 work) in 10 1346/1621 days = or 10.83 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Nancy = 28 days

And the number of days required to finish the same work by Margaret = 33 days

And the number of days required to finish the work by Sandra = 38 days

Thus, the number of days required to finish the work by Nancy, Margaret, and Sandra together = ?

Here a = 28 days

And, b = 33 days

And, c = 38 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Nancy, Margaret, and Sandra working together

= 28 × 33 × 38/28 × 33 + 28 × 38 + 33 × 38 days

= 35112/924 + 1064 + 1254 days

= 35112/3242 days

= 35112/3242 days

= 35112 ÷ 2/3242 ÷ 2 = 17556/1621 days

= 10 1346/1621 days or 10.83

Thus, Nancy, Margaret, and Sandra together will finish the work in 10 1346/1621 days or 10.83 days Answer


Similar Questions

(1) If Anthony can finish the work in 31 days and Jeffrey can finish the same work in 36 days, then in how many days both can finish the work together?

(2) If John can finish the work in 28 days and Richard can finish the same work in 44 days, then in how many days both can finish the work together?

(3) If David can finish the work in 10 days and Christopher can finish the same work in 14 days, then in how many days both can finish the work together?

(4) If Gary can finish the work in 67 days and Christian can finish the same work in 72 days, then in how many days both can finish the work together?

(5) Brandon can finish a work in 83 days. Samuel can finish the same work in 88 days while Gregory can finish the work in 93 days. How long will it take to finish it if they work together?

(6) If Andrew can finish the work in 41 days and Scott can finish the same work in 46 days, then in how many days both can finish the work together?

(7) Richard can finish a work in 17 days. Thomas can finish the same work in 22 days while Charles can finish the work in 27 days. How long will it take to finish it if they work together?

(8) If Barbara can finish the work in 13 days and Anthony can finish the same work in 16 days, then in how many days both can finish the work together?

(9) Steven can finish a work in 37 days. Andrew can finish the same work in 42 days while Joshua can finish the work in 47 days. How long will it take to finish it if they work together?

(10) If Sandra can finish the work in 31 days and Gary can finish the same work in 35 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©