Time and Work
MCQs Math


Question:     Steven can finish a work in 37 days. Andrew can finish the same work in 42 days while Joshua can finish the work in 47 days. How long will it take to finish it if they work together?


Correct Answer  13 4567/5267 days or 13.867 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Steven = 37 days

And, the number of days required to finish the same work by Andrew = 42 days

And, the number of days required to finish the same work by Joshua = 47 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 37 days the work is done by Steven = 1

∴ The work done by Steven in 1 day = 1/37

Similarly,

∵ In 42 days the work is done by Andrew = 1

∴ The work done by Andrew in 1 day = 1/42

Similarly,

∵ In 47 days the work is done by Joshua = 1

∴ The work done by Joshua in 1 day = 1/47 part

Now, the work done by Steven, Andrew, and Joshua together in 1 day

= Steven's 1 day work + Andrew's 1 day work + Joshua's 1 day work

= 1/37 + 1/42 + 1/47

= 1974 + 1739 + 1554/73038

= 5267/73038 part of work

This means in 1 day, 5267/73038 part of work is done by Steven, Andrew and Joshua working together.

Now, the number of days required to finish 5267/73038 part of work by Steven, Andrew, and Joshua working together = 1

∴ the number of days required to finish the whole work (1 work) by Steven + Andrew + Joshua together

= 1/5267/73038

= 1 × 73038/5267 = 73038/5267 days

= 13 4567/5267 days = or 13.867 days

Thus, Steven, Andrew, and Joshua working together will finish the total work (1 work) in 13 4567/5267 days = or 13.867 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Steven = 37 days

And the number of days required to finish the same work by Andrew = 42 days

And the number of days required to finish the work by Joshua = 47 days

Thus, the number of days required to finish the work by Steven, Andrew, and Joshua together = ?

Here a = 37 days

And, b = 42 days

And, c = 47 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Steven, Andrew, and Joshua working together

= 37 × 42 × 47/37 × 42 + 37 × 47 + 42 × 47 days

= 73038/1554 + 1739 + 1974 days

= 73038/5267 days

= 73038/5267 days

= 13 4567/5267 days or 13.867

Thus, Steven, Andrew, and Joshua together will finish the work in 13 4567/5267 days or 13.867 days Answer


Similar Questions

(1) If Brandon can finish the work in 83 days and Joe can finish the same work in 88 days, then in how many days both can finish the work together?

(2) If Susan can finish the work in 18 days and Donald can finish the same work in 23 days, then in how many days both can finish the work together?

(3) If Michelle can finish the work in 41 days and Samuel can finish the same work in 45 days, then in how many days both can finish the work together?

(4) Scott can finish a work in 81 days. Benjamin can finish the same work in 86 days while Samuel can finish the work in 91 days. How long will it take to finish it if they work together?

(5) If Janet can finish the work in 98 days and Russell can finish the same work in 103 days, then in how many days both can finish the work together?

(6) Barbara can finish a work in 12 days. Susan can finish the same work in 13 days while Jessica can finish the work in 14 days. How long will it take to finish it if they work together?

(7) If Jason can finish the work in 59 days and Douglas can finish the same work in 64 days, then in how many days both can finish the work together?

(8) If Donald can finish the work in 32 days and Nicholas can finish the same work in 35 days, then in how many days both can finish the work together?

(9) Kimberly can finish a work in 38 days. Donna can finish the same work in 43 days while Michelle can finish the work in 48 days. How long will it take to finish it if they work together?

(10) If Elizabeth can finish the work in 11 days and Daniel can finish the same work in 15 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©