Question:
Carol can finish a work in 46 days. Dorothy can finish the same work in 51 days while Melissa can finish the work in 56 days. How long will it take to finish it if they work together?
Correct Answer
16 3464/3889 days or 16.891 days
Solution And Explanation
Solution
Given,
The number of days required to finish a piece of work by Carol = 46 days
And, the number of days required to finish the same work by Dorothy = 51 days
And, the number of days required to finish the same work by Melissa = 56 days
Thus, the number of days required to finish the work by all of them if they work together = ?
Here,
∵ In 46 days the work is done by Carol = 1
∴ The work done by Carol in 1 day = 1/46
Similarly,
∵ In 51 days the work is done by Dorothy = 1
∴ The work done by Dorothy in 1 day = 1/51
Similarly,
∵ In 56 days the work is done by Melissa = 1
∴ The work done by Melissa in 1 day = 1/56 part
Now, the work done by Carol, Dorothy, and Melissa together in 1 day
= Carol's 1 day work + Dorothy's 1 day work + Melissa's 1 day work
= 1/46 + 1/51 + 1/56
= 1428 + 1288 + 1173/65688
= 3889/65688 part of work
This means in 1 day, 3889/65688 part of work is done by Carol, Dorothy and Melissa working together.
Now, the number of days required to finish 3889/65688 part of work by Carol, Dorothy, and Melissa working together = 1
∴ the number of days required to finish the whole work (1 work) by Carol + Dorothy + Melissa together
= 1/3889/65688
= 1 × 65688/3889 = 65688/3889 days
= 16 3464/3889 days = or 16.891 days
Thus, Carol, Dorothy, and Melissa working together will finish the total work (1 work) in 16 3464/3889 days = or 16.891 days Answer
Shortcut Trick to solve the problems based on time and work using formula
Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.
Here given,
The number of days required to finish the work by Carol = 46 days
And the number of days required to finish the same work by Dorothy = 51 days
And the number of days required to finish the work by Melissa = 56 days
Thus, the number of days required to finish the work by Carol, Dorothy, and Melissa together = ?
Here a = 46 days
And, b = 51 days
And, c = 56 days
Thus, using formula a × b × c/ab + ac + bc days
The number of days required to finish the work when Carol, Dorothy, and Melissa working together
= 46 × 51 × 56/46 × 51 + 46 × 56 + 51 × 56 days
= 131376/2346 + 2576 + 2856 days
= 131376/7778 days
= 131376/7778 days
= 131376 ÷ 2/7778 ÷ 2 = 65688/3889 days
= 16 3464/3889 days or 16.891
Thus, Carol, Dorothy, and Melissa together will finish the work in 16 3464/3889 days or 16.891 days Answer
Similar Questions
(1) If Myra can finish the work in 15 days and Sophia can finish the same work in 20 days, then in how many days they both can finish the work working together?
(2) Daniel can finish a work in 27 days. Anthony can finish the same work in 32 days while Mark can finish the work in 37 days. How long will it take to finish it if they work together?
(3) If Laura can finish the work in 62 days and Kyle can finish the same work in 67 days, then in how many days both can finish the work together?
(4) Jack can finish a work in 99 days. Jerry can finish the same work in 104 days while Tyler can finish the work in 109 days. How long will it take to finish it if they work together?
(5) Anthony can finish a work in 27 days. Mark can finish the same work in 28 days while Donald can finish the work in 29 days. How long will it take to finish it if they work together?
(6) Michelle can finish a work in 44 days. Amanda can finish the same work in 49 days while Dorothy can finish the work in 54 days. How long will it take to finish it if they work together?
(7) Stephanie can finish a work in 56 days. Sharon can finish the same work in 61 days while Laura can finish the work in 66 days. How long will it take to finish it if they work together?
(8) If Lisa can finish the work in 23 days and George can finish the same work in 26 days, then in how many days both can finish the work together?
(9) Brenda can finish a work in 76 days. Emma can finish the same work in 81 days while Nicole can finish the work in 86 days. How long will it take to finish it if they work together?
(10) Jessica can finish a work in 16 days. Sarah can finish the same work in 17 days while Karen can finish the work in 18 days. How long will it take to finish it if they work together?