Time and Work
MCQs Math


Question:     Dorothy can finish a work in 50 days. Deborah can finish the same work in 55 days while Stephanie can finish the work in 60 days. How long will it take to finish it if they work together?


Correct Answer  18 42/181 days or 18.232 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Dorothy = 50 days

And, the number of days required to finish the same work by Deborah = 55 days

And, the number of days required to finish the same work by Stephanie = 60 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 50 days the work is done by Dorothy = 1

∴ The work done by Dorothy in 1 day = 1/50

Similarly,

∵ In 55 days the work is done by Deborah = 1

∴ The work done by Deborah in 1 day = 1/55

Similarly,

∵ In 60 days the work is done by Stephanie = 1

∴ The work done by Stephanie in 1 day = 1/60 part

Now, the work done by Dorothy, Deborah, and Stephanie together in 1 day

= Dorothy's 1 day work + Deborah's 1 day work + Stephanie's 1 day work

= 1/50 + 1/55 + 1/60

= 66 + 60 + 55/3300

= 181/3300 part of work

This means in 1 day, 181/3300 part of work is done by Dorothy, Deborah and Stephanie working together.

Now, the number of days required to finish 181/3300 part of work by Dorothy, Deborah, and Stephanie working together = 1

∴ the number of days required to finish the whole work (1 work) by Dorothy + Deborah + Stephanie together

= 1/181/3300

= 1 × 3300/181 = 3300/181 days

= 18 42/181 days = or 18.232 days

Thus, Dorothy, Deborah, and Stephanie working together will finish the total work (1 work) in 18 42/181 days = or 18.232 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Dorothy = 50 days

And the number of days required to finish the same work by Deborah = 55 days

And the number of days required to finish the work by Stephanie = 60 days

Thus, the number of days required to finish the work by Dorothy, Deborah, and Stephanie together = ?

Here a = 50 days

And, b = 55 days

And, c = 60 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Dorothy, Deborah, and Stephanie working together

= 50 × 55 × 60/50 × 55 + 50 × 60 + 55 × 60 days

= 165000/2750 + 3000 + 3300 days

= 165000/9050 days

= 165000/9050 days

= 165000 ÷ 50/9050 ÷ 50 = 3300/181 days

= 18 42/181 days or 18.232

Thus, Dorothy, Deborah, and Stephanie together will finish the work in 18 42/181 days or 18.232 days Answer


Similar Questions

(1) Kenneth can finish a work in 45 days. Brian can finish the same work in 50 days while George can finish the work in 55 days. How long will it take to finish it if they work together?

(2) Samantha can finish a work in 86 days. Christine can finish the same work in 91 days while Debra can finish the work in 96 days. How long will it take to finish it if they work together?

(3) Jennifer can finish a work in 6 days. Linda can finish the same work in 7 days while Elizabeth can finish the work in 8 days. How long will it take to finish it if they work together?

(4) Susan can finish a work in 14 days. Jessica can finish the same work in 15 days while Sarah can finish the work in 16 days. How long will it take to finish it if they work together?

(5) Cynthia can finish a work in 64 days. Amy can finish the same work in 69 days while Angela can finish the work in 74 days. How long will it take to finish it if they work together?

(6) If Ashley can finish the work in 33 days and Eric can finish the same work in 36 days, then in how many days both can finish the work together?

(7) Lisa can finish a work in 22 days. Nancy can finish the same work in 23 days while Betty can finish the work in 24 days. How long will it take to finish it if they work together?

(8) William can finish a work in 11 days. Richard can finish the same work in 12 days while Joseph can finish the work in 13 days. How long will it take to finish it if they work together?

(9) Nicholas can finish a work in 69 days. Jonathan can finish the same work in 74 days while Stephen can finish the work in 79 days. How long will it take to finish it if they work together?

(10) Charles can finish a work in 23 days. Daniel can finish the same work in 28 days while Matthew can finish the work in 33 days. How long will it take to finish it if they work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©