Time and Work
MCQs Math


Question:     George can finish a work in 51 days. Ronald can finish the same work in 56 days while Edward can finish the work in 61 days. How long will it take to finish it if they work together?


Correct Answer  18 5322/9383 days or 18.567 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by George = 51 days

And, the number of days required to finish the same work by Ronald = 56 days

And, the number of days required to finish the same work by Edward = 61 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 51 days the work is done by George = 1

∴ The work done by George in 1 day = 1/51

Similarly,

∵ In 56 days the work is done by Ronald = 1

∴ The work done by Ronald in 1 day = 1/56

Similarly,

∵ In 61 days the work is done by Edward = 1

∴ The work done by Edward in 1 day = 1/61 part

Now, the work done by George, Ronald, and Edward together in 1 day

= George's 1 day work + Ronald's 1 day work + Edward's 1 day work

= 1/51 + 1/56 + 1/61

= 3416 + 3111 + 2856/174216

= 9383/174216 part of work

This means in 1 day, 9383/174216 part of work is done by George, Ronald and Edward working together.

Now, the number of days required to finish 9383/174216 part of work by George, Ronald, and Edward working together = 1

∴ the number of days required to finish the whole work (1 work) by George + Ronald + Edward together

= 1/9383/174216

= 1 × 174216/9383 = 174216/9383 days

= 18 5322/9383 days = or 18.567 days

Thus, George, Ronald, and Edward working together will finish the total work (1 work) in 18 5322/9383 days = or 18.567 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by George = 51 days

And the number of days required to finish the same work by Ronald = 56 days

And the number of days required to finish the work by Edward = 61 days

Thus, the number of days required to finish the work by George, Ronald, and Edward together = ?

Here a = 51 days

And, b = 56 days

And, c = 61 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when George, Ronald, and Edward working together

= 51 × 56 × 61/51 × 56 + 51 × 61 + 56 × 61 days

= 174216/2856 + 3111 + 3416 days

= 174216/9383 days

= 174216/9383 days

= 18 5322/9383 days or 18.567

Thus, George, Ronald, and Edward together will finish the work in 18 5322/9383 days or 18.567 days Answer


Similar Questions

(1) William can finish a work in 11 days. Richard can finish the same work in 12 days while Joseph can finish the work in 13 days. How long will it take to finish it if they work together?

(2) If Annie can finish a work in 3 days and Bobby can finish the same work in 6 days, then in how many days they both can finish the work working together?

(3) If Mark can finish the work in 33 days and Jacob can finish the same work in 38 days, then in how many days both can finish the work together?

(4) If Kimberly can finish the work in 35 days and Stephen can finish the same work in 39 days, then in how many days both can finish the work together?

(5) If Anthony can finish the work in 28 days and Jeffrey can finish the same work in 32 days, then in how many days both can finish the work together?

(6) If Shirley can finish the work in 72 days and Harold can finish the same work in 77 days, then in how many days both can finish the work together?

(7) Eric can finish a work in 71 days. Stephen can finish the same work in 76 days while Larry can finish the work in 81 days. How long will it take to finish it if they work together?

(8) Charles can finish a work in 23 days. Daniel can finish the same work in 28 days while Matthew can finish the work in 33 days. How long will it take to finish it if they work together?

(9) Sarah can finish a work in 18 days. Karen can finish the same work in 19 days while Lisa can finish the work in 20 days. How long will it take to finish it if they work together?

(10) Donna can finish a work in 38 days. Michelle can finish the same work in 39 days while Carol can finish the work in 40 days. How long will it take to finish it if they work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©