Question:     George can finish a work in 51 days. Ronald can finish the same work in 56 days while Edward can finish the work in 61 days. How long will it take to finish it if they work together?


Correct Answer  18 5322/9383 days or 18.567 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by George = 51 days

And, the number of days required to finish the same work by Ronald = 56 days

And, the number of days required to finish the same work by Edward = 61 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 51 days the work is done by George = 1

∴ The work done by George in 1 day = 1/51

Similarly,

∵ In 56 days the work is done by Ronald = 1

∴ The work done by Ronald in 1 day = 1/56

Similarly,

∵ In 61 days the work is done by Edward = 1

∴ The work done by Edward in 1 day = 1/61 part

Now, the work done by George, Ronald, and Edward together in 1 day

= George's 1 day work + Ronald's 1 day work + Edward's 1 day work

= 1/51 + 1/56 + 1/61

= 3416 + 3111 + 2856/174216

= 9383/174216 part of work

This means in 1 day, 9383/174216 part of work is done by George, Ronald and Edward working together.

Now, the number of days required to finish 9383/174216 part of work by George, Ronald, and Edward working together = 1

∴ the number of days required to finish the whole work (1 work) by George + Ronald + Edward together

= 1/9383/174216

= 1 × 174216/9383 = 174216/9383 days

= 18 5322/9383 days = or 18.567 days

Thus, George, Ronald, and Edward working together will finish the total work (1 work) in 18 5322/9383 days = or 18.567 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by George = 51 days

And the number of days required to finish the same work by Ronald = 56 days

And the number of days required to finish the work by Edward = 61 days

Thus, the number of days required to finish the work by George, Ronald, and Edward together = ?

Here a = 51 days

And, b = 56 days

And, c = 61 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when George, Ronald, and Edward working together

= 51 × 56 × 61/51 × 56 + 51 × 61 + 56 × 61 days

= 174216/2856 + 3111 + 3416 days

= 174216/9383 days

= 174216/9383 days

= 18 5322/9383 days or 18.567

Thus, George, Ronald, and Edward together will finish the work in 18 5322/9383 days or 18.567 days Answer


Similar Questions

(1) If Nancy can finish the work in 28 days and Ronald can finish the same work in 33 days, then in how many days both can finish the work together?

(2) If Andrew can finish the work in 38 days and Scott can finish the same work in 42 days, then in how many days both can finish the work together?

(3) If Jacob can finish the work in 65 days and Noah can finish the same work in 70 days, then in how many days both can finish the work together?

(4) If Ashley can finish the work in 36 days and Eric can finish the same work in 41 days, then in how many days both can finish the work together?

(5) Christine can finish a work in 90 days. Rachel can finish the same work in 95 days while Carolyn can finish the work in 100 days. How long will it take to finish it if they work together?

(6) If Mark can finish the work in 30 days and Jacob can finish the same work in 34 days, then in how many days both can finish the work together?

(7) If Barbara can finish the work in 13 days and Anthony can finish the same work in 16 days, then in how many days both can finish the work together?

(8) If Sarah can finish the work in 19 days and Joshua can finish the same work in 23 days, then in how many days both can finish the work together?

(9) If Ryan can finish the work in 63 days and Ethan can finish the same work in 68 days, then in how many days both can finish the work together?

(10) If Deborah can finish the work in 54 days and Aaron can finish the same work in 59 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©