Time and Work
MCQs Math


Question:     Deborah can finish a work in 54 days. Rebecca can finish the same work in 59 days while Sharon can finish the work in 64 days. How long will it take to finish it if they work together?


Correct Answer  19 2981/5209 days or 19.572 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Deborah = 54 days

And, the number of days required to finish the same work by Rebecca = 59 days

And, the number of days required to finish the same work by Sharon = 64 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 54 days the work is done by Deborah = 1

∴ The work done by Deborah in 1 day = 1/54

Similarly,

∵ In 59 days the work is done by Rebecca = 1

∴ The work done by Rebecca in 1 day = 1/59

Similarly,

∵ In 64 days the work is done by Sharon = 1

∴ The work done by Sharon in 1 day = 1/64 part

Now, the work done by Deborah, Rebecca, and Sharon together in 1 day

= Deborah's 1 day work + Rebecca's 1 day work + Sharon's 1 day work

= 1/54 + 1/59 + 1/64

= 1888 + 1728 + 1593/101952

= 5209/101952 part of work

This means in 1 day, 5209/101952 part of work is done by Deborah, Rebecca and Sharon working together.

Now, the number of days required to finish 5209/101952 part of work by Deborah, Rebecca, and Sharon working together = 1

∴ the number of days required to finish the whole work (1 work) by Deborah + Rebecca + Sharon together

= 1/5209/101952

= 1 × 101952/5209 = 101952/5209 days

= 19 2981/5209 days = or 19.572 days

Thus, Deborah, Rebecca, and Sharon working together will finish the total work (1 work) in 19 2981/5209 days = or 19.572 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Deborah = 54 days

And the number of days required to finish the same work by Rebecca = 59 days

And the number of days required to finish the work by Sharon = 64 days

Thus, the number of days required to finish the work by Deborah, Rebecca, and Sharon together = ?

Here a = 54 days

And, b = 59 days

And, c = 64 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Deborah, Rebecca, and Sharon working together

= 54 × 59 × 64/54 × 59 + 54 × 64 + 59 × 64 days

= 203904/3186 + 3456 + 3776 days

= 203904/10418 days

= 203904/10418 days

= 203904 ÷ 2/10418 ÷ 2 = 101952/5209 days

= 19 2981/5209 days or 19.572

Thus, Deborah, Rebecca, and Sharon together will finish the work in 19 2981/5209 days or 19.572 days Answer


Similar Questions

(1) If Brandon can finish the work in 83 days and Joe can finish the same work in 88 days, then in how many days both can finish the work together?

(2) If Ashley can finish the work in 36 days and Eric can finish the same work in 41 days, then in how many days both can finish the work together?

(3) James can finish a work in 5 days. John can finish the same work in 10 days while Michael can finish the work in 15 days. How long will it take to finish it if they work together?

(4) Pamela can finish a work in 78 days. Nicole can finish the same work in 83 days while Helen can finish the work in 88 days. How long will it take to finish it if they work together?

(5) If Barbara can finish the work in 16 days and Anthony can finish the same work in 21 days, then in how many days both can finish the work together?

(6) Rachel can finish a work in 94 days. Janet can finish the same work in 99 days while Catherine can finish the work in 104 days. How long will it take to finish it if they work together?

(7) Kimberly can finish a work in 34 days. Emily can finish the same work in 35 days while Donna can finish the work in 36 days. How long will it take to finish it if they work together?

(8) If Anthony can finish the work in 28 days and Jeffrey can finish the same work in 31 days, then in how many days both can finish the work together?

(9) If William can finish the work in 12 days and Matthew can finish the same work in 15 days, then in how many days both can finish the work together?

(10) Benjamin can finish a work in 85 days. Gregory can finish the same work in 90 days while Alexander can finish the work in 95 days. How long will it take to finish it if they work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©