Time and Work
MCQs Math


Question:     Deborah can finish a work in 54 days. Rebecca can finish the same work in 59 days while Sharon can finish the work in 64 days. How long will it take to finish it if they work together?


Correct Answer  19 2981/5209 days or 19.572 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Deborah = 54 days

And, the number of days required to finish the same work by Rebecca = 59 days

And, the number of days required to finish the same work by Sharon = 64 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 54 days the work is done by Deborah = 1

∴ The work done by Deborah in 1 day = 1/54

Similarly,

∵ In 59 days the work is done by Rebecca = 1

∴ The work done by Rebecca in 1 day = 1/59

Similarly,

∵ In 64 days the work is done by Sharon = 1

∴ The work done by Sharon in 1 day = 1/64 part

Now, the work done by Deborah, Rebecca, and Sharon together in 1 day

= Deborah's 1 day work + Rebecca's 1 day work + Sharon's 1 day work

= 1/54 + 1/59 + 1/64

= 1888 + 1728 + 1593/101952

= 5209/101952 part of work

This means in 1 day, 5209/101952 part of work is done by Deborah, Rebecca and Sharon working together.

Now, the number of days required to finish 5209/101952 part of work by Deborah, Rebecca, and Sharon working together = 1

∴ the number of days required to finish the whole work (1 work) by Deborah + Rebecca + Sharon together

= 1/5209/101952

= 1 × 101952/5209 = 101952/5209 days

= 19 2981/5209 days = or 19.572 days

Thus, Deborah, Rebecca, and Sharon working together will finish the total work (1 work) in 19 2981/5209 days = or 19.572 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Deborah = 54 days

And the number of days required to finish the same work by Rebecca = 59 days

And the number of days required to finish the work by Sharon = 64 days

Thus, the number of days required to finish the work by Deborah, Rebecca, and Sharon together = ?

Here a = 54 days

And, b = 59 days

And, c = 64 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Deborah, Rebecca, and Sharon working together

= 54 × 59 × 64/54 × 59 + 54 × 64 + 59 × 64 days

= 203904/3186 + 3456 + 3776 days

= 203904/10418 days

= 203904/10418 days

= 203904 ÷ 2/10418 ÷ 2 = 101952/5209 days

= 19 2981/5209 days or 19.572

Thus, Deborah, Rebecca, and Sharon together will finish the work in 19 2981/5209 days or 19.572 days Answer


Similar Questions

(1) If Eric can finish the work in 71 days and Gerald can finish the same work in 76 days, then in how many days both can finish the work together?

(2) Brenda can finish a work in 76 days. Emma can finish the same work in 81 days while Nicole can finish the work in 86 days. How long will it take to finish it if they work together?

(3) If Sandra can finish the work in 34 days and Gary can finish the same work in 39 days, then in how many days both can finish the work together?

(4) If Michelle can finish the work in 44 days and Samuel can finish the same work in 49 days, then in how many days both can finish the work together?

(5) If Emily can finish the work in 40 days and Justin can finish the same work in 45 days, then in how many days both can finish the work together?

(6) Christopher can finish a work in 21 days. Daniel can finish the same work in 22 days while Matthew can finish the work in 23 days. How long will it take to finish it if they work together?

(7) If Michael can finish the work in 8 days and Thomas can finish the same work in 11 days, then in how many days both can finish the work together?

(8) If Sharon can finish the work in 60 days and Zachary can finish the same work in 65 days, then in how many days both can finish the work together?

(9) Donna can finish a work in 42 days. Carol can finish the same work in 47 days while Amanda can finish the work in 52 days. How long will it take to finish it if they work together?

(10) If Andrew can finish the work in 38 days and Scott can finish the same work in 42 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©