Time and Work
MCQs Math


Question:     Stephanie can finish a work in 56 days. Sharon can finish the same work in 61 days while Laura can finish the work in 66 days. How long will it take to finish it if they work together?


Correct Answer  20 1348/5569 days or 20.242 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Stephanie = 56 days

And, the number of days required to finish the same work by Sharon = 61 days

And, the number of days required to finish the same work by Laura = 66 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 56 days the work is done by Stephanie = 1

∴ The work done by Stephanie in 1 day = 1/56

Similarly,

∵ In 61 days the work is done by Sharon = 1

∴ The work done by Sharon in 1 day = 1/61

Similarly,

∵ In 66 days the work is done by Laura = 1

∴ The work done by Laura in 1 day = 1/66 part

Now, the work done by Stephanie, Sharon, and Laura together in 1 day

= Stephanie's 1 day work + Sharon's 1 day work + Laura's 1 day work

= 1/56 + 1/61 + 1/66

= 2013 + 1848 + 1708/112728

= 5569/112728 part of work

This means in 1 day, 5569/112728 part of work is done by Stephanie, Sharon and Laura working together.

Now, the number of days required to finish 5569/112728 part of work by Stephanie, Sharon, and Laura working together = 1

∴ the number of days required to finish the whole work (1 work) by Stephanie + Sharon + Laura together

= 1/5569/112728

= 1 × 112728/5569 = 112728/5569 days

= 20 1348/5569 days = or 20.242 days

Thus, Stephanie, Sharon, and Laura working together will finish the total work (1 work) in 20 1348/5569 days = or 20.242 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Stephanie = 56 days

And the number of days required to finish the same work by Sharon = 61 days

And the number of days required to finish the work by Laura = 66 days

Thus, the number of days required to finish the work by Stephanie, Sharon, and Laura together = ?

Here a = 56 days

And, b = 61 days

And, c = 66 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Stephanie, Sharon, and Laura working together

= 56 × 61 × 66/56 × 61 + 56 × 66 + 61 × 66 days

= 225456/3416 + 3696 + 4026 days

= 225456/11138 days

= 225456/11138 days

= 225456 ÷ 2/11138 ÷ 2 = 112728/5569 days

= 20 1348/5569 days or 20.242

Thus, Stephanie, Sharon, and Laura together will finish the work in 20 1348/5569 days or 20.242 days Answer


Similar Questions

(1) If Kenneth can finish the work in 42 days and Gregory can finish the same work in 45 days, then in how many days both can finish the work together?

(2) If Michelle can finish the work in 41 days and Samuel can finish the same work in 44 days, then in how many days both can finish the work together?

(3) If Joshua can finish the work in 40 days and Benjamin can finish the same work in 43 days, then in how many days both can finish the work together?

(4) If Carol can finish the work in 43 days and Alexander can finish the same work in 46 days, then in how many days both can finish the work together?

(5) If Donna can finish the work in 39 days and Brandon can finish the same work in 42 days, then in how many days both can finish the work together?

(6) If Andrew can finish the work in 38 days and Scott can finish the same work in 41 days, then in how many days both can finish the work together?

(7) If Kenneth can finish the work in 45 days and Gregory can finish the same work in 50 days, then in how many days both can finish the work together?

(8) Timothy can finish a work in 49 days. Ronald can finish the same work in 50 days while Edward can finish the work in 51 days. How long will it take to finish it if they work together?

(9) If Kevin can finish the work in 44 days and Frank can finish the same work in 47 days, then in how many days both can finish the work together?

(10) If George can finish the work in 48 days and Dennis can finish the same work in 51 days, then in how many days both can finish the work together?