Question:     Laura can finish a work in 62 days. Kathleen can finish the same work in 67 days while Amy can finish the work in 72 days. How long will it take to finish it if they work together?


Correct Answer  22 1682/6721 days or 22.25 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Laura = 62 days

And, the number of days required to finish the same work by Kathleen = 67 days

And, the number of days required to finish the same work by Amy = 72 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 62 days the work is done by Laura = 1

∴ The work done by Laura in 1 day = 1/62

Similarly,

∵ In 67 days the work is done by Kathleen = 1

∴ The work done by Kathleen in 1 day = 1/67

Similarly,

∵ In 72 days the work is done by Amy = 1

∴ The work done by Amy in 1 day = 1/72 part

Now, the work done by Laura, Kathleen, and Amy together in 1 day

= Laura's 1 day work + Kathleen's 1 day work + Amy's 1 day work

= 1/62 + 1/67 + 1/72

= 2412 + 2232 + 2077/149544

= 6721/149544 part of work

This means in 1 day, 6721/149544 part of work is done by Laura, Kathleen and Amy working together.

Now, the number of days required to finish 6721/149544 part of work by Laura, Kathleen, and Amy working together = 1

∴ the number of days required to finish the whole work (1 work) by Laura + Kathleen + Amy together

= 1/6721/149544

= 1 × 149544/6721 = 149544/6721 days

= 22 1682/6721 days = or 22.25 days

Thus, Laura, Kathleen, and Amy working together will finish the total work (1 work) in 22 1682/6721 days = or 22.25 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Laura = 62 days

And the number of days required to finish the same work by Kathleen = 67 days

And the number of days required to finish the work by Amy = 72 days

Thus, the number of days required to finish the work by Laura, Kathleen, and Amy together = ?

Here a = 62 days

And, b = 67 days

And, c = 72 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Laura, Kathleen, and Amy working together

= 62 × 67 × 72/62 × 67 + 62 × 72 + 67 × 72 days

= 299088/4154 + 4464 + 4824 days

= 299088/13442 days

= 299088/13442 days

= 299088 ÷ 2/13442 ÷ 2 = 149544/6721 days

= 22 1682/6721 days or 22.25

Thus, Laura, Kathleen, and Amy together will finish the work in 22 1682/6721 days or 22.25 days Answer


Similar Questions

(1) If Samantha can finish the work in 86 days and Logan can finish the same work in 91 days, then in how many days both can finish the work together?

(2) Joshua can finish a work in 43 days. Kevin can finish the same work in 48 days while Brian can finish the work in 53 days. How long will it take to finish it if they work together?

(3) Jennifer can finish a work in 6 days. Linda can finish the same work in 7 days while Elizabeth can finish the work in 8 days. How long will it take to finish it if they work together?

(4) If Jessica can finish the work in 17 days and Paul can finish the same work in 21 days, then in how many days both can finish the work together?

(5) Betty can finish a work in 26 days. Margaret can finish the same work in 27 days while Sandra can finish the work in 28 days. How long will it take to finish it if they work together?

(6) If Anthony can finish the work in 31 days and Jeffrey can finish the same work in 36 days, then in how many days both can finish the work together?

(7) If Carol can finish the work in 43 days and Alexander can finish the same work in 46 days, then in how many days both can finish the work together?

(8) Emily can finish a work in 36 days. Donna can finish the same work in 37 days while Michelle can finish the work in 38 days. How long will it take to finish it if they work together?

(9) Shirley can finish a work in 72 days. Brenda can finish the same work in 77 days while Pamela can finish the work in 82 days. How long will it take to finish it if they work together?

(10) If Patricia can finish the work in 5 days and William can finish the same work in 9 days, then in how many days both can finish the work together?