Time and Work
MCQs Math


Question:     Jacob can finish a work in 65 days. Nicholas can finish the same work in 70 days while Eric can finish the work in 75 days. How long will it take to finish it if they work together?


Correct Answer  23 149/587 days or 23.254 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Jacob = 65 days

And, the number of days required to finish the same work by Nicholas = 70 days

And, the number of days required to finish the same work by Eric = 75 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 65 days the work is done by Jacob = 1

∴ The work done by Jacob in 1 day = 1/65

Similarly,

∵ In 70 days the work is done by Nicholas = 1

∴ The work done by Nicholas in 1 day = 1/70

Similarly,

∵ In 75 days the work is done by Eric = 1

∴ The work done by Eric in 1 day = 1/75 part

Now, the work done by Jacob, Nicholas, and Eric together in 1 day

= Jacob's 1 day work + Nicholas's 1 day work + Eric's 1 day work

= 1/65 + 1/70 + 1/75

= 210 + 195 + 182/13650

= 587/13650 part of work

This means in 1 day, 587/13650 part of work is done by Jacob, Nicholas and Eric working together.

Now, the number of days required to finish 587/13650 part of work by Jacob, Nicholas, and Eric working together = 1

∴ the number of days required to finish the whole work (1 work) by Jacob + Nicholas + Eric together

= 1/587/13650

= 1 × 13650/587 = 13650/587 days

= 23 149/587 days = or 23.254 days

Thus, Jacob, Nicholas, and Eric working together will finish the total work (1 work) in 23 149/587 days = or 23.254 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Jacob = 65 days

And the number of days required to finish the same work by Nicholas = 70 days

And the number of days required to finish the work by Eric = 75 days

Thus, the number of days required to finish the work by Jacob, Nicholas, and Eric together = ?

Here a = 65 days

And, b = 70 days

And, c = 75 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Jacob, Nicholas, and Eric working together

= 65 × 70 × 75/65 × 70 + 65 × 75 + 70 × 75 days

= 341250/4550 + 4875 + 5250 days

= 341250/14675 days

= 341250/14675 days

= 341250 ÷ 25/14675 ÷ 25 = 13650/587 days

= 23 149/587 days or 23.254

Thus, Jacob, Nicholas, and Eric together will finish the work in 23 149/587 days or 23.254 days Answer


Similar Questions

(1) If Stephen can finish the work in 75 days and Carl can finish the same work in 80 days, then in how many days both can finish the work together?

(2) If Nancy can finish the work in 25 days and Ronald can finish the same work in 29 days, then in how many days both can finish the work together?

(3) If Betty can finish the work in 27 days and Jason can finish the same work in 31 days, then in how many days both can finish the work together?

(4) If Lisa can finish the work in 23 days and George can finish the same work in 27 days, then in how many days both can finish the work together?

(5) If Dorothy can finish the work in 50 days and Jack can finish the same work in 55 days, then in how many days both can finish the work together?

(6) Jason can finish a work in 59 days. Ryan can finish the same work in 64 days while Jacob can finish the work in 69 days. How long will it take to finish it if they work together?

(7) If Karen can finish the work in 21 days and Kevin can finish the same work in 25 days, then in how many days both can finish the work together?

(8) If Gregory can finish the work in 89 days and Alan can finish the same work in 94 days, then in how many days both can finish the work together?

(9) If Thomas can finish the work in 18 days and Andrew can finish the same work in 21 days, then in how many days both can finish the work together?

(10) Emily can finish a work in 36 days. Donna can finish the same work in 37 days while Michelle can finish the work in 38 days. How long will it take to finish it if they work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©