Time and Work
MCQs Math


Question:     Nicholas can finish a work in 69 days. Jonathan can finish the same work in 74 days while Stephen can finish the work in 79 days. How long will it take to finish it if they work together?


Correct Answer  24 9702/16403 days or 24.591 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Nicholas = 69 days

And, the number of days required to finish the same work by Jonathan = 74 days

And, the number of days required to finish the same work by Stephen = 79 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 69 days the work is done by Nicholas = 1

∴ The work done by Nicholas in 1 day = 1/69

Similarly,

∵ In 74 days the work is done by Jonathan = 1

∴ The work done by Jonathan in 1 day = 1/74

Similarly,

∵ In 79 days the work is done by Stephen = 1

∴ The work done by Stephen in 1 day = 1/79 part

Now, the work done by Nicholas, Jonathan, and Stephen together in 1 day

= Nicholas's 1 day work + Jonathan's 1 day work + Stephen's 1 day work

= 1/69 + 1/74 + 1/79

= 5846 + 5451 + 5106/403374

= 16403/403374 part of work

This means in 1 day, 16403/403374 part of work is done by Nicholas, Jonathan and Stephen working together.

Now, the number of days required to finish 16403/403374 part of work by Nicholas, Jonathan, and Stephen working together = 1

∴ the number of days required to finish the whole work (1 work) by Nicholas + Jonathan + Stephen together

= 1/16403/403374

= 1 × 403374/16403 = 403374/16403 days

= 24 9702/16403 days = or 24.591 days

Thus, Nicholas, Jonathan, and Stephen working together will finish the total work (1 work) in 24 9702/16403 days = or 24.591 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Nicholas = 69 days

And the number of days required to finish the same work by Jonathan = 74 days

And the number of days required to finish the work by Stephen = 79 days

Thus, the number of days required to finish the work by Nicholas, Jonathan, and Stephen together = ?

Here a = 69 days

And, b = 74 days

And, c = 79 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Nicholas, Jonathan, and Stephen working together

= 69 × 74 × 79/69 × 74 + 69 × 79 + 74 × 79 days

= 403374/5106 + 5451 + 5846 days

= 403374/16403 days

= 403374/16403 days

= 24 9702/16403 days or 24.591

Thus, Nicholas, Jonathan, and Stephen together will finish the work in 24 9702/16403 days or 24.591 days Answer


Similar Questions

(1) If Karen can finish the work in 21 days and Kevin can finish the same work in 24 days, then in how many days both can finish the work together?

(2) If Barbara can finish the work in 16 days and Anthony can finish the same work in 21 days, then in how many days both can finish the work together?

(3) Janet can finish a work in 98 days. Maria can finish the same work in 103 days while Heather can finish the work in 108 days. How long will it take to finish it if they work together?

(4) Helen can finish a work in 84 days. Katherine can finish the same work in 89 days while Christine can finish the work in 94 days. How long will it take to finish it if they work together?

(5) Paul can finish a work in 39 days. Joshua can finish the same work in 44 days while Kenneth can finish the work in 49 days. How long will it take to finish it if they work together?

(6) Frank can finish a work in 93 days. Raymond can finish the same work in 98 days while Jack can finish the work in 103 days. How long will it take to finish it if they work together?

(7) If Annie can finish a work in 5 days and Bobby can finish the same work in 10 days, then in how many days they both can finish the work working together?

(8) If Annie can finish a work in 2 days and Bobby can finish the same work in 3 days, then in how many days they both can finish the work working together?

(9) If Gary can finish the work in 67 days and Christian can finish the same work in 72 days, then in how many days both can finish the work together?

(10) If Karen can finish the work in 21 days and Kevin can finish the same work in 25 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©