Time and Work
MCQs Math


Question:     Eric can finish a work in 71 days. Stephen can finish the same work in 76 days while Larry can finish the work in 81 days. How long will it take to finish it if they work together?


Correct Answer  25 4501/17303 days or 25.26 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Eric = 71 days

And, the number of days required to finish the same work by Stephen = 76 days

And, the number of days required to finish the same work by Larry = 81 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 71 days the work is done by Eric = 1

∴ The work done by Eric in 1 day = 1/71

Similarly,

∵ In 76 days the work is done by Stephen = 1

∴ The work done by Stephen in 1 day = 1/76

Similarly,

∵ In 81 days the work is done by Larry = 1

∴ The work done by Larry in 1 day = 1/81 part

Now, the work done by Eric, Stephen, and Larry together in 1 day

= Eric's 1 day work + Stephen's 1 day work + Larry's 1 day work

= 1/71 + 1/76 + 1/81

= 6156 + 5751 + 5396/437076

= 17303/437076 part of work

This means in 1 day, 17303/437076 part of work is done by Eric, Stephen and Larry working together.

Now, the number of days required to finish 17303/437076 part of work by Eric, Stephen, and Larry working together = 1

∴ the number of days required to finish the whole work (1 work) by Eric + Stephen + Larry together

= 1/17303/437076

= 1 × 437076/17303 = 437076/17303 days

= 25 4501/17303 days = or 25.26 days

Thus, Eric, Stephen, and Larry working together will finish the total work (1 work) in 25 4501/17303 days = or 25.26 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Eric = 71 days

And the number of days required to finish the same work by Stephen = 76 days

And the number of days required to finish the work by Larry = 81 days

Thus, the number of days required to finish the work by Eric, Stephen, and Larry together = ?

Here a = 71 days

And, b = 76 days

And, c = 81 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Eric, Stephen, and Larry working together

= 71 × 76 × 81/71 × 76 + 71 × 81 + 76 × 81 days

= 437076/5396 + 5751 + 6156 days

= 437076/17303 days

= 437076/17303 days

= 25 4501/17303 days or 25.26

Thus, Eric, Stephen, and Larry together will finish the work in 25 4501/17303 days or 25.26 days Answer


Similar Questions

(1) Patricia can finish a work in 8 days. Linda can finish the same work in 13 days while Elizabeth can finish the work in 18 days. How long will it take to finish it if they work together?

(2) Nicholas can finish a work in 69 days. Jonathan can finish the same work in 74 days while Stephen can finish the work in 79 days. How long will it take to finish it if they work together?

(3) If Andrew can finish the work in 38 days and Scott can finish the same work in 42 days, then in how many days both can finish the work together?

(4) If Anthony can finish the work in 28 days and Jeffrey can finish the same work in 32 days, then in how many days both can finish the work together?

(5) If Robert can finish a work in 5 days and Bob can finish the same work in 6 days, then in how many days they both can finish the work working together?

(6) If Carol can finish the work in 43 days and Alexander can finish the same work in 47 days, then in how many days both can finish the work together?

(7) If Annie can finish a work in 3 days and Bobby can finish the same work in 6 days, then in how many days they both can finish the work working together?

(8) Linda can finish a work in 8 days. Elizabeth can finish the same work in 9 days while Barbara can finish the work in 10 days. How long will it take to finish it if they work together?

(9) Carolyn can finish a work in 96 days. Catherine can finish the same work in 101 days while Maria can finish the work in 106 days. How long will it take to finish it if they work together?

(10) If Matthew can finish the work in 26 days and Edward can finish the same work in 29 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©