Question:
Shirley can finish a work in 72 days. Brenda can finish the same work in 77 days while Pamela can finish the work in 82 days. How long will it take to finish it if they work together?
Correct Answer
25 5279/8881 days or 25.594 days
Solution And Explanation
Solution
Given,
The number of days required to finish a piece of work by Shirley = 72 days
And, the number of days required to finish the same work by Brenda = 77 days
And, the number of days required to finish the same work by Pamela = 82 days
Thus, the number of days required to finish the work by all of them if they work together = ?
Here,
∵ In 72 days the work is done by Shirley = 1
∴ The work done by Shirley in 1 day = 1/72
Similarly,
∵ In 77 days the work is done by Brenda = 1
∴ The work done by Brenda in 1 day = 1/77
Similarly,
∵ In 82 days the work is done by Pamela = 1
∴ The work done by Pamela in 1 day = 1/82 part
Now, the work done by Shirley, Brenda, and Pamela together in 1 day
= Shirley's 1 day work + Brenda's 1 day work + Pamela's 1 day work
= 1/72 + 1/77 + 1/82
= 3157 + 2952 + 2772/227304
= 8881/227304 part of work
This means in 1 day, 8881/227304 part of work is done by Shirley, Brenda and Pamela working together.
Now, the number of days required to finish 8881/227304 part of work by Shirley, Brenda, and Pamela working together = 1
∴ the number of days required to finish the whole work (1 work) by Shirley + Brenda + Pamela together
= 1/8881/227304
= 1 × 227304/8881 = 227304/8881 days
= 25 5279/8881 days = or 25.594 days
Thus, Shirley, Brenda, and Pamela working together will finish the total work (1 work) in 25 5279/8881 days = or 25.594 days Answer
Shortcut Trick to solve the problems based on time and work using formula
Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.
Here given,
The number of days required to finish the work by Shirley = 72 days
And the number of days required to finish the same work by Brenda = 77 days
And the number of days required to finish the work by Pamela = 82 days
Thus, the number of days required to finish the work by Shirley, Brenda, and Pamela together = ?
Here a = 72 days
And, b = 77 days
And, c = 82 days
Thus, using formula a × b × c/ab + ac + bc days
The number of days required to finish the work when Shirley, Brenda, and Pamela working together
= 72 × 77 × 82/72 × 77 + 72 × 82 + 77 × 82 days
= 454608/5544 + 5904 + 6314 days
= 454608/17762 days
= 454608/17762 days
= 454608 ÷ 2/17762 ÷ 2 = 227304/8881 days
= 25 5279/8881 days or 25.594
Thus, Shirley, Brenda, and Pamela together will finish the work in 25 5279/8881 days or 25.594 days Answer
Similar Questions
(1) Sarah can finish a work in 22 days. Lisa can finish the same work in 27 days while Nancy can finish the work in 32 days. How long will it take to finish it if they work together?
(2) Stephanie can finish a work in 56 days. Sharon can finish the same work in 61 days while Laura can finish the work in 66 days. How long will it take to finish it if they work together?
(3) If Joseph can finish the work in 16 days and Steven can finish the same work in 19 days, then in how many days both can finish the work together?
(4) If Anthony can finish the work in 28 days and Jeffrey can finish the same work in 32 days, then in how many days both can finish the work together?
(5) If John can finish the work in 6 days and Richard can finish the same work in 10 days, then in how many days both can finish the work together?
(6) Ashley can finish a work in 32 days. Kimberly can finish the same work in 33 days while Emily can finish the work in 34 days. How long will it take to finish it if they work together?
(7) If Barbara can finish the work in 13 days and Anthony can finish the same work in 16 days, then in how many days both can finish the work together?
(8) Patrick can finish a work in 95 days. Jack can finish the same work in 100 days while Dennis can finish the work in 105 days. How long will it take to finish it if they work together?
(9) If Jessica can finish the work in 17 days and Paul can finish the same work in 21 days, then in how many days both can finish the work together?
(10) If Kevin can finish the work in 44 days and Frank can finish the same work in 48 days, then in how many days both can finish the work together?