Question:
Jonathan can finish a work in 73 days. Larry can finish the same work in 78 days while Justin can finish the work in 83 days. How long will it take to finish it if they work together?
Correct Answer
25 16927/18227 days or 25.929 days
Solution And Explanation
Solution
Given,
The number of days required to finish a piece of work by Jonathan = 73 days
And, the number of days required to finish the same work by Larry = 78 days
And, the number of days required to finish the same work by Justin = 83 days
Thus, the number of days required to finish the work by all of them if they work together = ?
Here,
∵ In 73 days the work is done by Jonathan = 1
∴ The work done by Jonathan in 1 day = 1/73
Similarly,
∵ In 78 days the work is done by Larry = 1
∴ The work done by Larry in 1 day = 1/78
Similarly,
∵ In 83 days the work is done by Justin = 1
∴ The work done by Justin in 1 day = 1/83 part
Now, the work done by Jonathan, Larry, and Justin together in 1 day
= Jonathan's 1 day work + Larry's 1 day work + Justin's 1 day work
= 1/73 + 1/78 + 1/83
= 6474 + 6059 + 5694/472602
= 18227/472602 part of work
This means in 1 day, 18227/472602 part of work is done by Jonathan, Larry and Justin working together.
Now, the number of days required to finish 18227/472602 part of work by Jonathan, Larry, and Justin working together = 1
∴ the number of days required to finish the whole work (1 work) by Jonathan + Larry + Justin together
= 1/18227/472602
= 1 × 472602/18227 = 472602/18227 days
= 25 16927/18227 days = or 25.929 days
Thus, Jonathan, Larry, and Justin working together will finish the total work (1 work) in 25 16927/18227 days = or 25.929 days Answer
Shortcut Trick to solve the problems based on time and work using formula
Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.
Here given,
The number of days required to finish the work by Jonathan = 73 days
And the number of days required to finish the same work by Larry = 78 days
And the number of days required to finish the work by Justin = 83 days
Thus, the number of days required to finish the work by Jonathan, Larry, and Justin together = ?
Here a = 73 days
And, b = 78 days
And, c = 83 days
Thus, using formula a × b × c/ab + ac + bc days
The number of days required to finish the work when Jonathan, Larry, and Justin working together
= 73 × 78 × 83/73 × 78 + 73 × 83 + 78 × 83 days
= 472602/5694 + 6059 + 6474 days
= 472602/18227 days
= 472602/18227 days
= 25 16927/18227 days or 25.929
Thus, Jonathan, Larry, and Justin together will finish the work in 25 16927/18227 days or 25.929 days Answer
Similar Questions
(1) Nicole can finish a work in 82 days. Samantha can finish the same work in 87 days while Katherine can finish the work in 92 days. How long will it take to finish it if they work together?
(2) If Richard can finish the work in 14 days and Mark can finish the same work in 17 days, then in how many days both can finish the work together?
(3) Patricia can finish a work in 8 days. Linda can finish the same work in 13 days while Elizabeth can finish the work in 18 days. How long will it take to finish it if they work together?
(4) If Patricia can finish the work in 5 days and William can finish the same work in 8 days, then in how many days both can finish the work together?
(5) If Rachel can finish the work in 94 days and Roy can finish the same work in 99 days, then in how many days both can finish the work together?
(6) Stephanie can finish a work in 56 days. Sharon can finish the same work in 61 days while Laura can finish the work in 66 days. How long will it take to finish it if they work together?
(7) If Robert can finish the work in 7 days and David can finish the same work in 12 days, then in how many days both can finish the work together?
(8) Amanda can finish a work in 48 days. Melissa can finish the same work in 53 days while Deborah can finish the work in 58 days. How long will it take to finish it if they work together?
(9) Jonathan can finish a work in 73 days. Larry can finish the same work in 78 days while Justin can finish the work in 83 days. How long will it take to finish it if they work together?
(10) If Cynthia can finish the work in 64 days and Walter can finish the same work in 69 days, then in how many days both can finish the work together?