Time and Work
MCQs Math


Question:     Jonathan can finish a work in 73 days. Larry can finish the same work in 78 days while Justin can finish the work in 83 days. How long will it take to finish it if they work together?


Correct Answer  25 16927/18227 days or 25.929 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Jonathan = 73 days

And, the number of days required to finish the same work by Larry = 78 days

And, the number of days required to finish the same work by Justin = 83 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 73 days the work is done by Jonathan = 1

∴ The work done by Jonathan in 1 day = 1/73

Similarly,

∵ In 78 days the work is done by Larry = 1

∴ The work done by Larry in 1 day = 1/78

Similarly,

∵ In 83 days the work is done by Justin = 1

∴ The work done by Justin in 1 day = 1/83 part

Now, the work done by Jonathan, Larry, and Justin together in 1 day

= Jonathan's 1 day work + Larry's 1 day work + Justin's 1 day work

= 1/73 + 1/78 + 1/83

= 6474 + 6059 + 5694/472602

= 18227/472602 part of work

This means in 1 day, 18227/472602 part of work is done by Jonathan, Larry and Justin working together.

Now, the number of days required to finish 18227/472602 part of work by Jonathan, Larry, and Justin working together = 1

∴ the number of days required to finish the whole work (1 work) by Jonathan + Larry + Justin together

= 1/18227/472602

= 1 × 472602/18227 = 472602/18227 days

= 25 16927/18227 days = or 25.929 days

Thus, Jonathan, Larry, and Justin working together will finish the total work (1 work) in 25 16927/18227 days = or 25.929 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Jonathan = 73 days

And the number of days required to finish the same work by Larry = 78 days

And the number of days required to finish the work by Justin = 83 days

Thus, the number of days required to finish the work by Jonathan, Larry, and Justin together = ?

Here a = 73 days

And, b = 78 days

And, c = 83 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Jonathan, Larry, and Justin working together

= 73 × 78 × 83/73 × 78 + 73 × 83 + 78 × 83 days

= 472602/5694 + 6059 + 6474 days

= 472602/18227 days

= 472602/18227 days

= 25 16927/18227 days or 25.929

Thus, Jonathan, Larry, and Justin together will finish the work in 25 16927/18227 days or 25.929 days Answer


Similar Questions

(1) Melissa can finish a work in 48 days. Deborah can finish the same work in 49 days while Stephanie can finish the work in 50 days. How long will it take to finish it if they work together?

(2) If William can finish the work in 12 days and Matthew can finish the same work in 15 days, then in how many days both can finish the work together?

(3) If Andrew can finish the work in 38 days and Scott can finish the same work in 41 days, then in how many days both can finish the work together?

(4) If Robert can finish a work in 5 days and Bob can finish the same work in 6 days, then in how many days they both can finish the work working together?

(5) Michelle can finish a work in 44 days. Amanda can finish the same work in 49 days while Dorothy can finish the work in 54 days. How long will it take to finish it if they work together?

(6) Stephen can finish a work in 75 days. Justin can finish the same work in 80 days while Scott can finish the work in 85 days. How long will it take to finish it if they work together?

(7) Brian can finish a work in 45 days. George can finish the same work in 46 days while Timothy can finish the work in 47 days. How long will it take to finish it if they work together?

(8) If Stephanie can finish the work in 56 days and Adam can finish the same work in 61 days, then in how many days both can finish the work together?

(9) Patricia can finish a work in 8 days. Linda can finish the same work in 13 days while Elizabeth can finish the work in 18 days. How long will it take to finish it if they work together?