Time and Work
MCQs Math


Question:     Anna can finish a work in 74 days. Pamela can finish the same work in 79 days while Emma can finish the work in 84 days. How long will it take to finish it if they work together?


Correct Answer  26 2458/9349 days or 26.263 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Anna = 74 days

And, the number of days required to finish the same work by Pamela = 79 days

And, the number of days required to finish the same work by Emma = 84 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 74 days the work is done by Anna = 1

∴ The work done by Anna in 1 day = 1/74

Similarly,

∵ In 79 days the work is done by Pamela = 1

∴ The work done by Pamela in 1 day = 1/79

Similarly,

∵ In 84 days the work is done by Emma = 1

∴ The work done by Emma in 1 day = 1/84 part

Now, the work done by Anna, Pamela, and Emma together in 1 day

= Anna's 1 day work + Pamela's 1 day work + Emma's 1 day work

= 1/74 + 1/79 + 1/84

= 3318 + 3108 + 2923/245532

= 9349/245532 part of work

This means in 1 day, 9349/245532 part of work is done by Anna, Pamela and Emma working together.

Now, the number of days required to finish 9349/245532 part of work by Anna, Pamela, and Emma working together = 1

∴ the number of days required to finish the whole work (1 work) by Anna + Pamela + Emma together

= 1/9349/245532

= 1 × 245532/9349 = 245532/9349 days

= 26 2458/9349 days = or 26.263 days

Thus, Anna, Pamela, and Emma working together will finish the total work (1 work) in 26 2458/9349 days = or 26.263 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Anna = 74 days

And the number of days required to finish the same work by Pamela = 79 days

And the number of days required to finish the work by Emma = 84 days

Thus, the number of days required to finish the work by Anna, Pamela, and Emma together = ?

Here a = 74 days

And, b = 79 days

And, c = 84 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Anna, Pamela, and Emma working together

= 74 × 79 × 84/74 × 79 + 74 × 84 + 79 × 84 days

= 491064/5846 + 6216 + 6636 days

= 491064/18698 days

= 491064/18698 days

= 491064 ÷ 2/18698 ÷ 2 = 245532/9349 days

= 26 2458/9349 days or 26.263

Thus, Anna, Pamela, and Emma together will finish the work in 26 2458/9349 days or 26.263 days Answer


Similar Questions

(1) Dorothy can finish a work in 46 days. Melissa can finish the same work in 47 days while Deborah can finish the work in 48 days. How long will it take to finish it if they work together?

(2) Nancy can finish a work in 28 days. Margaret can finish the same work in 33 days while Sandra can finish the work in 38 days. How long will it take to finish it if they work together?

(3) If Edward can finish the work in 57 days and Nathan can finish the same work in 62 days, then in how many days both can finish the work together?

(4) Debra can finish a work in 92 days. Carolyn can finish the same work in 97 days while Janet can finish the work in 102 days. How long will it take to finish it if they work together?

(5) If Raymond can finish the work in 97 days and Eugene can finish the same work in 102 days, then in how many days both can finish the work together?

(6) Sarah can finish a work in 22 days. Lisa can finish the same work in 27 days while Nancy can finish the work in 32 days. How long will it take to finish it if they work together?

(7) Steven can finish a work in 33 days. Paul can finish the same work in 34 days while Andrew can finish the work in 35 days. How long will it take to finish it if they work together?

(8) If Joshua can finish the work in 40 days and Benjamin can finish the same work in 43 days, then in how many days both can finish the work together?

(9) John can finish a work in 5 days. Michael can finish the same work in 6 days while David can finish the work in 7 days. How long will it take to finish it if they work together?

(10) If Kenneth can finish the work in 45 days and Gregory can finish the same work in 50 days, then in how many days both can finish the work together?