Time and Work
MCQs Math


Question:     Scott can finish a work in 81 days. Benjamin can finish the same work in 86 days while Samuel can finish the work in 91 days. How long will it take to finish it if they work together?


Correct Answer  28 13342/22163 days or 28.602 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Scott = 81 days

And, the number of days required to finish the same work by Benjamin = 86 days

And, the number of days required to finish the same work by Samuel = 91 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 81 days the work is done by Scott = 1

∴ The work done by Scott in 1 day = 1/81

Similarly,

∵ In 86 days the work is done by Benjamin = 1

∴ The work done by Benjamin in 1 day = 1/86

Similarly,

∵ In 91 days the work is done by Samuel = 1

∴ The work done by Samuel in 1 day = 1/91 part

Now, the work done by Scott, Benjamin, and Samuel together in 1 day

= Scott's 1 day work + Benjamin's 1 day work + Samuel's 1 day work

= 1/81 + 1/86 + 1/91

= 7826 + 7371 + 6966/633906

= 22163/633906 part of work

This means in 1 day, 22163/633906 part of work is done by Scott, Benjamin and Samuel working together.

Now, the number of days required to finish 22163/633906 part of work by Scott, Benjamin, and Samuel working together = 1

∴ the number of days required to finish the whole work (1 work) by Scott + Benjamin + Samuel together

= 1/22163/633906

= 1 × 633906/22163 = 633906/22163 days

= 28 13342/22163 days = or 28.602 days

Thus, Scott, Benjamin, and Samuel working together will finish the total work (1 work) in 28 13342/22163 days = or 28.602 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Scott = 81 days

And the number of days required to finish the same work by Benjamin = 86 days

And the number of days required to finish the work by Samuel = 91 days

Thus, the number of days required to finish the work by Scott, Benjamin, and Samuel together = ?

Here a = 81 days

And, b = 86 days

And, c = 91 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Scott, Benjamin, and Samuel working together

= 81 × 86 × 91/81 × 86 + 81 × 91 + 86 × 91 days

= 633906/6966 + 7371 + 7826 days

= 633906/22163 days

= 633906/22163 days

= 28 13342/22163 days or 28.602

Thus, Scott, Benjamin, and Samuel together will finish the work in 28 13342/22163 days or 28.602 days Answer


Similar Questions

(1) If Barbara can finish the work in 35 days and Anthony can finish the same work in 51 days, then in how many days both can finish the work together?

(2) Brian can finish a work in 45 days. George can finish the same work in 46 days while Timothy can finish the work in 47 days. How long will it take to finish it if they work together?

(3) If Gregory can finish the work in 89 days and Alan can finish the same work in 94 days, then in how many days both can finish the work together?

(4) If Jason can finish the work in 59 days and Douglas can finish the same work in 64 days, then in how many days both can finish the work together?

(5) If Kimberly can finish the work in 38 days and Stephen can finish the same work in 43 days, then in how many days both can finish the work together?

(6) If Karen can finish the work in 21 days and Kevin can finish the same work in 24 days, then in how many days both can finish the work together?

(7) If Alexander can finish the work in 91 days and Wayne can finish the same work in 96 days, then in how many days both can finish the work together?

(8) If Raymond can finish the work in 97 days and Eugene can finish the same work in 102 days, then in how many days both can finish the work together?

(9) If Robert can finish the work in 26 days and David can finish the same work in 42 days, then in how many days both can finish the work together?

(10) If Janet can finish the work in 98 days and Russell can finish the same work in 103 days, then in how many days both can finish the work together?