Time and Work
MCQs Math


Question:     Brandon can finish a work in 83 days. Samuel can finish the same work in 88 days while Gregory can finish the work in 93 days. How long will it take to finish it if they work together?


Correct Answer  29 6269/23207 days or 29.27 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Brandon = 83 days

And, the number of days required to finish the same work by Samuel = 88 days

And, the number of days required to finish the same work by Gregory = 93 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 83 days the work is done by Brandon = 1

∴ The work done by Brandon in 1 day = 1/83

Similarly,

∵ In 88 days the work is done by Samuel = 1

∴ The work done by Samuel in 1 day = 1/88

Similarly,

∵ In 93 days the work is done by Gregory = 1

∴ The work done by Gregory in 1 day = 1/93 part

Now, the work done by Brandon, Samuel, and Gregory together in 1 day

= Brandon's 1 day work + Samuel's 1 day work + Gregory's 1 day work

= 1/83 + 1/88 + 1/93

= 8184 + 7719 + 7304/679272

= 23207/679272 part of work

This means in 1 day, 23207/679272 part of work is done by Brandon, Samuel and Gregory working together.

Now, the number of days required to finish 23207/679272 part of work by Brandon, Samuel, and Gregory working together = 1

∴ the number of days required to finish the whole work (1 work) by Brandon + Samuel + Gregory together

= 1/23207/679272

= 1 × 679272/23207 = 679272/23207 days

= 29 6269/23207 days = or 29.27 days

Thus, Brandon, Samuel, and Gregory working together will finish the total work (1 work) in 29 6269/23207 days = or 29.27 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Brandon = 83 days

And the number of days required to finish the same work by Samuel = 88 days

And the number of days required to finish the work by Gregory = 93 days

Thus, the number of days required to finish the work by Brandon, Samuel, and Gregory together = ?

Here a = 83 days

And, b = 88 days

And, c = 93 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Brandon, Samuel, and Gregory working together

= 83 × 88 × 93/83 × 88 + 83 × 93 + 88 × 93 days

= 679272/7304 + 7719 + 8184 days

= 679272/23207 days

= 679272/23207 days

= 29 6269/23207 days or 29.27

Thus, Brandon, Samuel, and Gregory together will finish the work in 29 6269/23207 days or 29.27 days Answer


Similar Questions

(1) If Jessica can finish the work in 17 days and Paul can finish the same work in 21 days, then in how many days both can finish the work together?

(2) If Charles can finish the work in 20 days and Kenneth can finish the same work in 23 days, then in how many days both can finish the work together?

(3) Margaret can finish a work in 28 days. Sandra can finish the same work in 29 days while Ashley can finish the work in 30 days. How long will it take to finish it if they work together?

(4) If Richard can finish the work in 36 days and Mark can finish the same work in 52 days, then in how many days both can finish the work together?

(5) If Jack can finish the work in 99 days and Bobby can finish the same work in 104 days, then in how many days both can finish the work together?

(6) If Pamela can finish the work in 78 days and Dylan can finish the same work in 83 days, then in how many days both can finish the work together?

(7) If Barbara can finish the work in 35 days and Anthony can finish the same work in 51 days, then in how many days both can finish the work together?

(8) If Donna can finish the work in 39 days and Brandon can finish the same work in 43 days, then in how many days both can finish the work together?

(9) Donald can finish a work in 31 days. Steven can finish the same work in 32 days while Paul can finish the work in 33 days. How long will it take to finish it if they work together?

(10) If Carol can finish the work in 43 days and Alexander can finish the same work in 46 days, then in how many days both can finish the work together?