Question:     Samantha can finish a work in 86 days. Christine can finish the same work in 91 days while Debra can finish the work in 96 days. How long will it take to finish it if they work together?


Correct Answer  30 3378/12409 days or 30.272 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Samantha = 86 days

And, the number of days required to finish the same work by Christine = 91 days

And, the number of days required to finish the same work by Debra = 96 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 86 days the work is done by Samantha = 1

∴ The work done by Samantha in 1 day = 1/86

Similarly,

∵ In 91 days the work is done by Christine = 1

∴ The work done by Christine in 1 day = 1/91

Similarly,

∵ In 96 days the work is done by Debra = 1

∴ The work done by Debra in 1 day = 1/96 part

Now, the work done by Samantha, Christine, and Debra together in 1 day

= Samantha's 1 day work + Christine's 1 day work + Debra's 1 day work

= 1/86 + 1/91 + 1/96

= 4368 + 4128 + 3913/375648

= 12409/375648 part of work

This means in 1 day, 12409/375648 part of work is done by Samantha, Christine and Debra working together.

Now, the number of days required to finish 12409/375648 part of work by Samantha, Christine, and Debra working together = 1

∴ the number of days required to finish the whole work (1 work) by Samantha + Christine + Debra together

= 1/12409/375648

= 1 × 375648/12409 = 375648/12409 days

= 30 3378/12409 days = or 30.272 days

Thus, Samantha, Christine, and Debra working together will finish the total work (1 work) in 30 3378/12409 days = or 30.272 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Samantha = 86 days

And the number of days required to finish the same work by Christine = 91 days

And the number of days required to finish the work by Debra = 96 days

Thus, the number of days required to finish the work by Samantha, Christine, and Debra together = ?

Here a = 86 days

And, b = 91 days

And, c = 96 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Samantha, Christine, and Debra working together

= 86 × 91 × 96/86 × 91 + 86 × 96 + 91 × 96 days

= 751296/7826 + 8256 + 8736 days

= 751296/24818 days

= 751296/24818 days

= 751296 ÷ 2/24818 ÷ 2 = 375648/12409 days

= 30 3378/12409 days or 30.272

Thus, Samantha, Christine, and Debra together will finish the work in 30 3378/12409 days or 30.272 days Answer


Similar Questions

(1) If Susan can finish the work in 18 days and Donald can finish the same work in 23 days, then in how many days both can finish the work together?

(2) Jeffrey can finish a work in 61 days. Jacob can finish the same work in 66 days while Gary can finish the work in 71 days. How long will it take to finish it if they work together?

(3) If Janet can finish the work in 98 days and Russell can finish the same work in 103 days, then in how many days both can finish the work together?

(4) If Annie can finish a work in 2 days and Bobby can finish the same work in 3 days, then in how many days they both can finish the work working together?

(5) If Richard can finish the work in 17 days and Mark can finish the same work in 22 days, then in how many days both can finish the work together?

(6) If Christopher can finish the work in 22 days and Brian can finish the same work in 25 days, then in how many days both can finish the work together?

(7) If Barbara can finish the work in 16 days and Anthony can finish the same work in 21 days, then in how many days both can finish the work together?

(8) If Larry can finish the work in 77 days and Lawrence can finish the same work in 82 days, then in how many days both can finish the work together?

(9) If Richard can finish the work in 36 days and Mark can finish the same work in 52 days, then in how many days both can finish the work together?

(10) Donald can finish a work in 35 days. Paul can finish the same work in 40 days while Andrew can finish the work in 45 days. How long will it take to finish it if they work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©