Time and Work
MCQs Math


Question:     Katherine can finish a work in 88 days. Debra can finish the same work in 93 days while Rachel can finish the work in 98 days. How long will it take to finish it if they work together?


Correct Answer  30 12186/12961 days or 30.94 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Katherine = 88 days

And, the number of days required to finish the same work by Debra = 93 days

And, the number of days required to finish the same work by Rachel = 98 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 88 days the work is done by Katherine = 1

∴ The work done by Katherine in 1 day = 1/88

Similarly,

∵ In 93 days the work is done by Debra = 1

∴ The work done by Debra in 1 day = 1/93

Similarly,

∵ In 98 days the work is done by Rachel = 1

∴ The work done by Rachel in 1 day = 1/98 part

Now, the work done by Katherine, Debra, and Rachel together in 1 day

= Katherine's 1 day work + Debra's 1 day work + Rachel's 1 day work

= 1/88 + 1/93 + 1/98

= 4557 + 4312 + 4092/401016

= 12961/401016 part of work

This means in 1 day, 12961/401016 part of work is done by Katherine, Debra and Rachel working together.

Now, the number of days required to finish 12961/401016 part of work by Katherine, Debra, and Rachel working together = 1

∴ the number of days required to finish the whole work (1 work) by Katherine + Debra + Rachel together

= 1/12961/401016

= 1 × 401016/12961 = 401016/12961 days

= 30 12186/12961 days = or 30.94 days

Thus, Katherine, Debra, and Rachel working together will finish the total work (1 work) in 30 12186/12961 days = or 30.94 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Katherine = 88 days

And the number of days required to finish the same work by Debra = 93 days

And the number of days required to finish the work by Rachel = 98 days

Thus, the number of days required to finish the work by Katherine, Debra, and Rachel together = ?

Here a = 88 days

And, b = 93 days

And, c = 98 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Katherine, Debra, and Rachel working together

= 88 × 93 × 98/88 × 93 + 88 × 98 + 93 × 98 days

= 802032/8184 + 8624 + 9114 days

= 802032/25922 days

= 802032/25922 days

= 802032 ÷ 2/25922 ÷ 2 = 401016/12961 days

= 30 12186/12961 days or 30.94

Thus, Katherine, Debra, and Rachel together will finish the work in 30 12186/12961 days or 30.94 days Answer


Similar Questions

(1) Deborah can finish a work in 54 days. Rebecca can finish the same work in 59 days while Sharon can finish the work in 64 days. How long will it take to finish it if they work together?

(2) Donna can finish a work in 42 days. Carol can finish the same work in 47 days while Amanda can finish the work in 52 days. How long will it take to finish it if they work together?

(3) Kevin can finish a work in 47 days. George can finish the same work in 52 days while Timothy can finish the work in 57 days. How long will it take to finish it if they work together?

(4) Anthony can finish a work in 27 days. Mark can finish the same work in 28 days while Donald can finish the work in 29 days. How long will it take to finish it if they work together?

(5) Matthew can finish a work in 29 days. Mark can finish the same work in 34 days while Donald can finish the work in 39 days. How long will it take to finish it if they work together?

(6) If Donna can finish the work in 39 days and Brandon can finish the same work in 42 days, then in how many days both can finish the work together?

(7) If Joshua can finish the work in 40 days and Benjamin can finish the same work in 43 days, then in how many days both can finish the work together?

(8) Susan can finish a work in 18 days. Sarah can finish the same work in 23 days while Karen can finish the work in 28 days. How long will it take to finish it if they work together?

(9) If Charles can finish the work in 20 days and Kenneth can finish the same work in 24 days, then in how many days both can finish the work together?

(10) If Emily can finish the work in 37 days and Justin can finish the same work in 41 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©