Time and Work
MCQs Math


Question:     Christine can finish a work in 90 days. Rachel can finish the same work in 95 days while Carolyn can finish the work in 100 days. How long will it take to finish it if they work together?


Correct Answer  31 329/541 days or 31.608 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Christine = 90 days

And, the number of days required to finish the same work by Rachel = 95 days

And, the number of days required to finish the same work by Carolyn = 100 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 90 days the work is done by Christine = 1

∴ The work done by Christine in 1 day = 1/90

Similarly,

∵ In 95 days the work is done by Rachel = 1

∴ The work done by Rachel in 1 day = 1/95

Similarly,

∵ In 100 days the work is done by Carolyn = 1

∴ The work done by Carolyn in 1 day = 1/100 part

Now, the work done by Christine, Rachel, and Carolyn together in 1 day

= Christine's 1 day work + Rachel's 1 day work + Carolyn's 1 day work

= 1/90 + 1/95 + 1/100

= 190 + 180 + 171/17100

= 541/17100 part of work

This means in 1 day, 541/17100 part of work is done by Christine, Rachel and Carolyn working together.

Now, the number of days required to finish 541/17100 part of work by Christine, Rachel, and Carolyn working together = 1

∴ the number of days required to finish the whole work (1 work) by Christine + Rachel + Carolyn together

= 1/541/17100

= 1 × 17100/541 = 17100/541 days

= 31 329/541 days = or 31.608 days

Thus, Christine, Rachel, and Carolyn working together will finish the total work (1 work) in 31 329/541 days = or 31.608 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Christine = 90 days

And the number of days required to finish the same work by Rachel = 95 days

And the number of days required to finish the work by Carolyn = 100 days

Thus, the number of days required to finish the work by Christine, Rachel, and Carolyn together = ?

Here a = 90 days

And, b = 95 days

And, c = 100 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Christine, Rachel, and Carolyn working together

= 90 × 95 × 100/90 × 95 + 90 × 100 + 95 × 100 days

= 855000/8550 + 9000 + 9500 days

= 855000/27050 days

= 855000/27050 days

= 855000 ÷ 50/27050 ÷ 50 = 17100/541 days

= 31 329/541 days or 31.608

Thus, Christine, Rachel, and Carolyn together will finish the work in 31 329/541 days or 31.608 days Answer


Similar Questions

(1) Mary can finish a work in 6 days. Jennifer can finish the same work in 11 days while Linda can finish the work in 16 days. How long will it take to finish it if they work together?

(2) Sharon can finish a work in 60 days. Cynthia can finish the same work in 65 days while Kathleen can finish the work in 70 days. How long will it take to finish it if they work together?

(3) Lisa can finish a work in 22 days. Nancy can finish the same work in 23 days while Betty can finish the work in 24 days. How long will it take to finish it if they work together?

(4) If Jennifer can finish the work in 29 days and Joseph can finish the same work in 45 days, then in how many days both can finish the work together?

(5) If Joshua can finish the work in 40 days and Benjamin can finish the same work in 43 days, then in how many days both can finish the work together?

(6) Benjamin can finish a work in 85 days. Gregory can finish the same work in 90 days while Alexander can finish the work in 95 days. How long will it take to finish it if they work together?

(7) If Kimberly can finish the work in 38 days and Stephen can finish the same work in 43 days, then in how many days both can finish the work together?

(8) If Elizabeth can finish the work in 33 days and Daniel can finish the same work in 49 days, then in how many days both can finish the work together?

(9) Melissa can finish a work in 52 days. Stephanie can finish the same work in 57 days while Rebecca can finish the work in 62 days. How long will it take to finish it if they work together?

(10) If Jeffrey can finish the work in 61 days and Peter can finish the same work in 66 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©