Time and Work
MCQs Math


Question:     Rachel can finish a work in 94 days. Janet can finish the same work in 99 days while Catherine can finish the work in 104 days. How long will it take to finish it if they work together?


Correct Answer  32 13864/14689 days or 32.944 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Rachel = 94 days

And, the number of days required to finish the same work by Janet = 99 days

And, the number of days required to finish the same work by Catherine = 104 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 94 days the work is done by Rachel = 1

∴ The work done by Rachel in 1 day = 1/94

Similarly,

∵ In 99 days the work is done by Janet = 1

∴ The work done by Janet in 1 day = 1/99

Similarly,

∵ In 104 days the work is done by Catherine = 1

∴ The work done by Catherine in 1 day = 1/104 part

Now, the work done by Rachel, Janet, and Catherine together in 1 day

= Rachel's 1 day work + Janet's 1 day work + Catherine's 1 day work

= 1/94 + 1/99 + 1/104

= 5148 + 4888 + 4653/483912

= 14689/483912 part of work

This means in 1 day, 14689/483912 part of work is done by Rachel, Janet and Catherine working together.

Now, the number of days required to finish 14689/483912 part of work by Rachel, Janet, and Catherine working together = 1

∴ the number of days required to finish the whole work (1 work) by Rachel + Janet + Catherine together

= 1/14689/483912

= 1 × 483912/14689 = 483912/14689 days

= 32 13864/14689 days = or 32.944 days

Thus, Rachel, Janet, and Catherine working together will finish the total work (1 work) in 32 13864/14689 days = or 32.944 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Rachel = 94 days

And the number of days required to finish the same work by Janet = 99 days

And the number of days required to finish the work by Catherine = 104 days

Thus, the number of days required to finish the work by Rachel, Janet, and Catherine together = ?

Here a = 94 days

And, b = 99 days

And, c = 104 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Rachel, Janet, and Catherine working together

= 94 × 99 × 104/94 × 99 + 94 × 104 + 99 × 104 days

= 967824/9306 + 9776 + 10296 days

= 967824/29378 days

= 967824/29378 days

= 967824 ÷ 2/29378 ÷ 2 = 483912/14689 days

= 32 13864/14689 days or 32.944

Thus, Rachel, Janet, and Catherine together will finish the work in 32 13864/14689 days or 32.944 days Answer


Similar Questions

(1) If Margaret can finish the work in 32 days and Ryan can finish the same work in 37 days, then in how many days both can finish the work together?

(2) If Debra can finish the work in 92 days and Elijah can finish the same work in 97 days, then in how many days both can finish the work together?

(3) If Michelle can finish the work in 41 days and Samuel can finish the same work in 44 days, then in how many days both can finish the work together?

(4) If Justin can finish the work in 79 days and Jesse can finish the same work in 84 days, then in how many days both can finish the work together?

(5) If A can do a piece of work in 2 days, B can do the same piece of work in 3 days, while C alone can do the same work in 4 days. Find the number of days to finish the work when they all will work together.

(6) If Jennifer can finish the work in 7 days and Joseph can finish the same work in 10 days, then in how many days both can finish the work together?

(7) If Kenneth can finish the work in 42 days and Gregory can finish the same work in 45 days, then in how many days both can finish the work together?

(8) Michael can finish a work in 7 days. David can finish the same work in 8 days while William can finish the work in 9 days. How long will it take to finish it if they work together?

(9) Dorothy can finish a work in 46 days. Melissa can finish the same work in 47 days while Deborah can finish the work in 48 days. How long will it take to finish it if they work together?

(10) If Richard can finish the work in 14 days and Mark can finish the same work in 17 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©