Time and Work
MCQs Math


Question:     Rachel can finish a work in 94 days. Janet can finish the same work in 99 days while Catherine can finish the work in 104 days. How long will it take to finish it if they work together?


Correct Answer  32 13864/14689 days or 32.944 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Rachel = 94 days

And, the number of days required to finish the same work by Janet = 99 days

And, the number of days required to finish the same work by Catherine = 104 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 94 days the work is done by Rachel = 1

∴ The work done by Rachel in 1 day = 1/94

Similarly,

∵ In 99 days the work is done by Janet = 1

∴ The work done by Janet in 1 day = 1/99

Similarly,

∵ In 104 days the work is done by Catherine = 1

∴ The work done by Catherine in 1 day = 1/104 part

Now, the work done by Rachel, Janet, and Catherine together in 1 day

= Rachel's 1 day work + Janet's 1 day work + Catherine's 1 day work

= 1/94 + 1/99 + 1/104

= 5148 + 4888 + 4653/483912

= 14689/483912 part of work

This means in 1 day, 14689/483912 part of work is done by Rachel, Janet and Catherine working together.

Now, the number of days required to finish 14689/483912 part of work by Rachel, Janet, and Catherine working together = 1

∴ the number of days required to finish the whole work (1 work) by Rachel + Janet + Catherine together

= 1/14689/483912

= 1 × 483912/14689 = 483912/14689 days

= 32 13864/14689 days = or 32.944 days

Thus, Rachel, Janet, and Catherine working together will finish the total work (1 work) in 32 13864/14689 days = or 32.944 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Rachel = 94 days

And the number of days required to finish the same work by Janet = 99 days

And the number of days required to finish the work by Catherine = 104 days

Thus, the number of days required to finish the work by Rachel, Janet, and Catherine together = ?

Here a = 94 days

And, b = 99 days

And, c = 104 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Rachel, Janet, and Catherine working together

= 94 × 99 × 104/94 × 99 + 94 × 104 + 99 × 104 days

= 967824/9306 + 9776 + 10296 days

= 967824/29378 days

= 967824/29378 days

= 967824 ÷ 2/29378 ÷ 2 = 483912/14689 days

= 32 13864/14689 days or 32.944

Thus, Rachel, Janet, and Catherine together will finish the work in 32 13864/14689 days or 32.944 days Answer


Similar Questions

(1) David can finish a work in 9 days. William can finish the same work in 10 days while Richard can finish the work in 11 days. How long will it take to finish it if they work together?

(2) Shirley can finish a work in 72 days. Brenda can finish the same work in 77 days while Pamela can finish the work in 82 days. How long will it take to finish it if they work together?

(3) If Paul can finish the work in 39 days and Larry can finish the same work in 44 days, then in how many days both can finish the work together?

(4) Jason can finish a work in 59 days. Ryan can finish the same work in 64 days while Jacob can finish the work in 69 days. How long will it take to finish it if they work together?

(5) If Paul can finish the work in 36 days and Larry can finish the same work in 39 days, then in how many days both can finish the work together?

(6) If Lisa can finish the work in 23 days and George can finish the same work in 26 days, then in how many days both can finish the work together?

(7) If Patricia can finish the work in 5 days and William can finish the same work in 9 days, then in how many days both can finish the work together?

(8) If Jessica can finish the work in 20 days and Paul can finish the same work in 25 days, then in how many days both can finish the work together?

(9) If Susan can finish the work in 18 days and Donald can finish the same work in 23 days, then in how many days both can finish the work together?

(10) If Annie can finish a work in 3 days and Bobby can finish the same work in 6 days, then in how many days they both can finish the work working together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©