Time and Work
MCQs Math


Question:     Patrick can finish a work in 95 days. Jack can finish the same work in 100 days while Dennis can finish the work in 105 days. How long will it take to finish it if they work together?


Correct Answer  33 333/1199 days or 33.278 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Patrick = 95 days

And, the number of days required to finish the same work by Jack = 100 days

And, the number of days required to finish the same work by Dennis = 105 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 95 days the work is done by Patrick = 1

∴ The work done by Patrick in 1 day = 1/95

Similarly,

∵ In 100 days the work is done by Jack = 1

∴ The work done by Jack in 1 day = 1/100

Similarly,

∵ In 105 days the work is done by Dennis = 1

∴ The work done by Dennis in 1 day = 1/105 part

Now, the work done by Patrick, Jack, and Dennis together in 1 day

= Patrick's 1 day work + Jack's 1 day work + Dennis's 1 day work

= 1/95 + 1/100 + 1/105

= 420 + 399 + 380/39900

= 1199/39900 part of work

This means in 1 day, 1199/39900 part of work is done by Patrick, Jack and Dennis working together.

Now, the number of days required to finish 1199/39900 part of work by Patrick, Jack, and Dennis working together = 1

∴ the number of days required to finish the whole work (1 work) by Patrick + Jack + Dennis together

= 1/1199/39900

= 1 × 39900/1199 = 39900/1199 days

= 33 333/1199 days = or 33.278 days

Thus, Patrick, Jack, and Dennis working together will finish the total work (1 work) in 33 333/1199 days = or 33.278 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Patrick = 95 days

And the number of days required to finish the same work by Jack = 100 days

And the number of days required to finish the work by Dennis = 105 days

Thus, the number of days required to finish the work by Patrick, Jack, and Dennis together = ?

Here a = 95 days

And, b = 100 days

And, c = 105 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Patrick, Jack, and Dennis working together

= 95 × 100 × 105/95 × 100 + 95 × 105 + 100 × 105 days

= 997500/9500 + 9975 + 10500 days

= 997500/29975 days

= 997500/29975 days

= 997500 ÷ 25/29975 ÷ 25 = 39900/1199 days

= 33 333/1199 days or 33.278

Thus, Patrick, Jack, and Dennis together will finish the work in 33 333/1199 days or 33.278 days Answer


Similar Questions

(1) Nicholas can finish a work in 69 days. Jonathan can finish the same work in 74 days while Stephen can finish the work in 79 days. How long will it take to finish it if they work together?

(2) Karen can finish a work in 20 days. Lisa can finish the same work in 21 days while Nancy can finish the work in 22 days. How long will it take to finish it if they work together?

(3) Rachel can finish a work in 94 days. Janet can finish the same work in 99 days while Catherine can finish the work in 104 days. How long will it take to finish it if they work together?

(4) Betty can finish a work in 30 days. Sandra can finish the same work in 35 days while Ashley can finish the work in 40 days. How long will it take to finish it if they work together?

(5) If Barbara can finish the work in 13 days and Anthony can finish the same work in 17 days, then in how many days both can finish the work together?

(6) Raymond can finish a work in 97 days. Dennis can finish the same work in 102 days while Jerry can finish the work in 107 days. How long will it take to finish it if they work together?

(7) If Nancy can finish the work in 25 days and Ronald can finish the same work in 29 days, then in how many days both can finish the work together?

(8) If Matthew can finish the work in 26 days and Edward can finish the same work in 30 days, then in how many days both can finish the work together?

(9) Dorothy can finish a work in 46 days. Melissa can finish the same work in 47 days while Deborah can finish the work in 48 days. How long will it take to finish it if they work together?

(10) If Laura can finish the work in 62 days and Kyle can finish the same work in 67 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©