Time and Work
MCQs Math


Question:     Jennifer can finish a work in 6 days. Linda can finish the same work in 7 days while Elizabeth can finish the work in 8 days. How long will it take to finish it if they work together?


Correct Answer  2 22/73 days or 2.301 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Jennifer = 6 days

And, the number of days required to finish the same work by Linda = 7 days

And, the number of days required to finish the same work by Elizabeth = 8 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 6 days the work is done by Jennifer = 1

∴ The work done by Jennifer in 1 day = 1/6

Similarly,

∵ In 7 days the work is done by Linda = 1

∴ The work done by Linda in 1 day = 1/7

Similarly,

∵ In 8 days the work is done by Elizabeth = 1

∴ The work done by Elizabeth in 1 day = 1/8 part

Now, the work done by Jennifer, Linda, and Elizabeth together in 1 day

= Jennifer's 1 day work + Linda's 1 day work + Elizabeth's 1 day work

= 1/6 + 1/7 + 1/8

= 28 + 24 + 21/168

= 73/168 part of work

This means in 1 day, 73/168 part of work is done by Jennifer, Linda and Elizabeth working together.

Now, the number of days required to finish 73/168 part of work by Jennifer, Linda, and Elizabeth working together = 1

∴ the number of days required to finish the whole work (1 work) by Jennifer + Linda + Elizabeth together

= 1/73/168

= 1 × 168/73 = 168/73 days

= 2 22/73 days = or 2.301 days

Thus, Jennifer, Linda, and Elizabeth working together will finish the total work (1 work) in 2 22/73 days = or 2.301 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Jennifer = 6 days

And the number of days required to finish the same work by Linda = 7 days

And the number of days required to finish the work by Elizabeth = 8 days

Thus, the number of days required to finish the work by Jennifer, Linda, and Elizabeth together = ?

Here a = 6 days

And, b = 7 days

And, c = 8 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Jennifer, Linda, and Elizabeth working together

= 6 × 7 × 8/6 × 7 + 6 × 8 + 7 × 8 days

= 336/42 + 48 + 56 days

= 336/146 days

= 336/146 days

= 336 ÷ 2/146 ÷ 2 = 168/73 days

= 2 22/73 days or 2.301

Thus, Jennifer, Linda, and Elizabeth together will finish the work in 2 22/73 days or 2.301 days Answer


Similar Questions

(1) If Mark can finish the work in 30 days and Jacob can finish the same work in 34 days, then in how many days both can finish the work together?

(2) If Sarah can finish the work in 22 days and Joshua can finish the same work in 27 days, then in how many days both can finish the work together?

(3) Pamela can finish a work in 78 days. Nicole can finish the same work in 83 days while Helen can finish the work in 88 days. How long will it take to finish it if they work together?

(4) Jason can finish a work in 59 days. Ryan can finish the same work in 64 days while Jacob can finish the work in 69 days. How long will it take to finish it if they work together?

(5) Gary can finish a work in 67 days. Eric can finish the same work in 72 days while Jonathan can finish the work in 77 days. How long will it take to finish it if they work together?

(6) If Myra can finish the work in 15 days and Sophia can finish the same work in 20 days, then in how many days they both can finish the work working together?

(7) Daniel can finish a work in 23 days. Matthew can finish the same work in 24 days while Anthony can finish the work in 25 days. How long will it take to finish it if they work together?

(8) If Michelle can finish the work in 41 days and Samuel can finish the same work in 45 days, then in how many days both can finish the work together?

(9) Ronald can finish a work in 55 days. Jason can finish the same work in 60 days while Jeffrey can finish the work in 65 days. How long will it take to finish it if they work together?

(10) Steven can finish a work in 33 days. Paul can finish the same work in 34 days while Andrew can finish the work in 35 days. How long will it take to finish it if they work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©