Question:     David can finish a work in 9 days. William can finish the same work in 10 days while Richard can finish the work in 11 days. How long will it take to finish it if they work together?


Correct Answer  3 93/299 days or 3.311 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by David = 9 days

And, the number of days required to finish the same work by William = 10 days

And, the number of days required to finish the same work by Richard = 11 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 9 days the work is done by David = 1

∴ The work done by David in 1 day = 1/9

Similarly,

∵ In 10 days the work is done by William = 1

∴ The work done by William in 1 day = 1/10

Similarly,

∵ In 11 days the work is done by Richard = 1

∴ The work done by Richard in 1 day = 1/11 part

Now, the work done by David, William, and Richard together in 1 day

= David's 1 day work + William's 1 day work + Richard's 1 day work

= 1/9 + 1/10 + 1/11

= 110 + 99 + 90/990

= 299/990 part of work

This means in 1 day, 299/990 part of work is done by David, William and Richard working together.

Now, the number of days required to finish 299/990 part of work by David, William, and Richard working together = 1

∴ the number of days required to finish the whole work (1 work) by David + William + Richard together

= 1/299/990

= 1 × 990/299 = 990/299 days

= 3 93/299 days = or 3.311 days

Thus, David, William, and Richard working together will finish the total work (1 work) in 3 93/299 days = or 3.311 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by David = 9 days

And the number of days required to finish the same work by William = 10 days

And the number of days required to finish the work by Richard = 11 days

Thus, the number of days required to finish the work by David, William, and Richard together = ?

Here a = 9 days

And, b = 10 days

And, c = 11 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when David, William, and Richard working together

= 9 × 10 × 11/9 × 10 + 9 × 11 + 10 × 11 days

= 990/90 + 99 + 110 days

= 990/299 days

= 990/299 days

= 3 93/299 days or 3.311

Thus, David, William, and Richard together will finish the work in 3 93/299 days or 3.311 days Answer


Similar Questions

(1) If Patricia can finish the work in 5 days and William can finish the same work in 8 days, then in how many days both can finish the work together?

(2) Amanda can finish a work in 48 days. Melissa can finish the same work in 53 days while Deborah can finish the work in 58 days. How long will it take to finish it if they work together?

(3) Nancy can finish a work in 28 days. Margaret can finish the same work in 33 days while Sandra can finish the work in 38 days. How long will it take to finish it if they work together?

(4) If Anthony can finish the work in 28 days and Jeffrey can finish the same work in 31 days, then in how many days both can finish the work together?

(5) If Emily can finish the work in 40 days and Justin can finish the same work in 45 days, then in how many days both can finish the work together?

(6) If Michelle can finish the work in 41 days and Samuel can finish the same work in 44 days, then in how many days both can finish the work together?

(7) If Brian can finish the work in 49 days and Raymond can finish the same work in 54 days, then in how many days both can finish the work together?

(8) Ashley can finish a work in 36 days. Emily can finish the same work in 41 days while Donna can finish the work in 46 days. How long will it take to finish it if they work together?

(9) If Linda can finish the work in 9 days and Charles can finish the same work in 13 days, then in how many days both can finish the work together?

(10) If Stephen can finish the work in 75 days and Carl can finish the same work in 80 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©