Question:     Barbara can finish a work in 12 days. Susan can finish the same work in 13 days while Jessica can finish the work in 14 days. How long will it take to finish it if they work together?


Correct Answer  4 80/253 days or 4.316 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Barbara = 12 days

And, the number of days required to finish the same work by Susan = 13 days

And, the number of days required to finish the same work by Jessica = 14 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 12 days the work is done by Barbara = 1

∴ The work done by Barbara in 1 day = 1/12

Similarly,

∵ In 13 days the work is done by Susan = 1

∴ The work done by Susan in 1 day = 1/13

Similarly,

∵ In 14 days the work is done by Jessica = 1

∴ The work done by Jessica in 1 day = 1/14 part

Now, the work done by Barbara, Susan, and Jessica together in 1 day

= Barbara's 1 day work + Susan's 1 day work + Jessica's 1 day work

= 1/12 + 1/13 + 1/14

= 91 + 84 + 78/1092

= 253/1092 part of work

This means in 1 day, 253/1092 part of work is done by Barbara, Susan and Jessica working together.

Now, the number of days required to finish 253/1092 part of work by Barbara, Susan, and Jessica working together = 1

∴ the number of days required to finish the whole work (1 work) by Barbara + Susan + Jessica together

= 1/253/1092

= 1 × 1092/253 = 1092/253 days

= 4 80/253 days = or 4.316 days

Thus, Barbara, Susan, and Jessica working together will finish the total work (1 work) in 4 80/253 days = or 4.316 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Barbara = 12 days

And the number of days required to finish the same work by Susan = 13 days

And the number of days required to finish the work by Jessica = 14 days

Thus, the number of days required to finish the work by Barbara, Susan, and Jessica together = ?

Here a = 12 days

And, b = 13 days

And, c = 14 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Barbara, Susan, and Jessica working together

= 12 × 13 × 14/12 × 13 + 12 × 14 + 13 × 14 days

= 2184/156 + 168 + 182 days

= 2184/506 days

= 2184/506 days

= 2184 ÷ 2/506 ÷ 2 = 1092/253 days

= 4 80/253 days or 4.316

Thus, Barbara, Susan, and Jessica together will finish the work in 4 80/253 days or 4.316 days Answer


Similar Questions

(1) If Cynthia can finish the work in 64 days and Walter can finish the same work in 69 days, then in how many days both can finish the work together?

(2) If Sarah can finish the work in 19 days and Joshua can finish the same work in 23 days, then in how many days both can finish the work together?

(3) If Margaret can finish the work in 32 days and Ryan can finish the same work in 37 days, then in how many days both can finish the work together?

(4) Kenneth can finish a work in 41 days. Kevin can finish the same work in 42 days while Brian can finish the work in 43 days. How long will it take to finish it if they work together?

(5) If Margaret can finish the work in 29 days and Ryan can finish the same work in 33 days, then in how many days both can finish the work together?

(6) Raymond can finish a work in 97 days. Dennis can finish the same work in 102 days while Jerry can finish the work in 107 days. How long will it take to finish it if they work together?

(7) If Betty can finish the work in 27 days and Jason can finish the same work in 30 days, then in how many days both can finish the work together?

(8) If Jennifer can finish the work in 7 days and Joseph can finish the same work in 11 days, then in how many days both can finish the work together?

(9) Sarah can finish a work in 22 days. Lisa can finish the same work in 27 days while Nancy can finish the work in 32 days. How long will it take to finish it if they work together?

(10) If Robert can finish the work in 7 days and David can finish the same work in 12 days, then in how many days both can finish the work together?