Question:
Joseph can finish a work in 15 days. Thomas can finish the same work in 16 days while Charles can finish the work in 17 days. How long will it take to finish it if they work together?
Correct Answer
5 245/767 days or 5.319 days
Solution And Explanation
Solution
Given,
The number of days required to finish a piece of work by Joseph = 15 days
And, the number of days required to finish the same work by Thomas = 16 days
And, the number of days required to finish the same work by Charles = 17 days
Thus, the number of days required to finish the work by all of them if they work together = ?
Here,
∵ In 15 days the work is done by Joseph = 1
∴ The work done by Joseph in 1 day = 1/15
Similarly,
∵ In 16 days the work is done by Thomas = 1
∴ The work done by Thomas in 1 day = 1/16
Similarly,
∵ In 17 days the work is done by Charles = 1
∴ The work done by Charles in 1 day = 1/17 part
Now, the work done by Joseph, Thomas, and Charles together in 1 day
= Joseph's 1 day work + Thomas's 1 day work + Charles's 1 day work
= 1/15 + 1/16 + 1/17
= 272 + 255 + 240/4080
= 767/4080 part of work
This means in 1 day, 767/4080 part of work is done by Joseph, Thomas and Charles working together.
Now, the number of days required to finish 767/4080 part of work by Joseph, Thomas, and Charles working together = 1
∴ the number of days required to finish the whole work (1 work) by Joseph + Thomas + Charles together
= 1/767/4080
= 1 × 4080/767 = 4080/767 days
= 5 245/767 days = or 5.319 days
Thus, Joseph, Thomas, and Charles working together will finish the total work (1 work) in 5 245/767 days = or 5.319 days Answer
Shortcut Trick to solve the problems based on time and work using formula
Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.
Here given,
The number of days required to finish the work by Joseph = 15 days
And the number of days required to finish the same work by Thomas = 16 days
And the number of days required to finish the work by Charles = 17 days
Thus, the number of days required to finish the work by Joseph, Thomas, and Charles together = ?
Here a = 15 days
And, b = 16 days
And, c = 17 days
Thus, using formula a × b × c/ab + ac + bc days
The number of days required to finish the work when Joseph, Thomas, and Charles working together
= 15 × 16 × 17/15 × 16 + 15 × 17 + 16 × 17 days
= 4080/240 + 255 + 272 days
= 4080/767 days
= 4080/767 days
= 5 245/767 days or 5.319
Thus, Joseph, Thomas, and Charles together will finish the work in 5 245/767 days or 5.319 days Answer
Similar Questions
(1) If Joshua can finish the work in 40 days and Benjamin can finish the same work in 44 days, then in how many days both can finish the work together?
(2) If Patrick can finish the work in 95 days and Vincent can finish the same work in 100 days, then in how many days both can finish the work together?
(3) If George can finish the work in 48 days and Dennis can finish the same work in 51 days, then in how many days both can finish the work together?
(4) If Robert can finish a work in 5 days and Bob can finish the same work in 6 days, then in how many days they both can finish the work working together?
(5) If Dorothy can finish the work in 50 days and Jack can finish the same work in 55 days, then in how many days both can finish the work together?
(6) George can finish a work in 51 days. Ronald can finish the same work in 56 days while Edward can finish the work in 61 days. How long will it take to finish it if they work together?
(7) Scott can finish a work in 81 days. Benjamin can finish the same work in 86 days while Samuel can finish the work in 91 days. How long will it take to finish it if they work together?
(8) If Jason can finish the work in 59 days and Douglas can finish the same work in 64 days, then in how many days both can finish the work together?
(9) If George can finish the work in 48 days and Dennis can finish the same work in 52 days, then in how many days both can finish the work together?
(10) If Patricia can finish the work in 27 days and William can finish the same work in 43 days, then in how many days both can finish the work together?