Time and Work
MCQs Math


Question:     Joseph can finish a work in 15 days. Thomas can finish the same work in 16 days while Charles can finish the work in 17 days. How long will it take to finish it if they work together?


Correct Answer  5 245/767 days or 5.319 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Joseph = 15 days

And, the number of days required to finish the same work by Thomas = 16 days

And, the number of days required to finish the same work by Charles = 17 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 15 days the work is done by Joseph = 1

∴ The work done by Joseph in 1 day = 1/15

Similarly,

∵ In 16 days the work is done by Thomas = 1

∴ The work done by Thomas in 1 day = 1/16

Similarly,

∵ In 17 days the work is done by Charles = 1

∴ The work done by Charles in 1 day = 1/17 part

Now, the work done by Joseph, Thomas, and Charles together in 1 day

= Joseph's 1 day work + Thomas's 1 day work + Charles's 1 day work

= 1/15 + 1/16 + 1/17

= 272 + 255 + 240/4080

= 767/4080 part of work

This means in 1 day, 767/4080 part of work is done by Joseph, Thomas and Charles working together.

Now, the number of days required to finish 767/4080 part of work by Joseph, Thomas, and Charles working together = 1

∴ the number of days required to finish the whole work (1 work) by Joseph + Thomas + Charles together

= 1/767/4080

= 1 × 4080/767 = 4080/767 days

= 5 245/767 days = or 5.319 days

Thus, Joseph, Thomas, and Charles working together will finish the total work (1 work) in 5 245/767 days = or 5.319 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Joseph = 15 days

And the number of days required to finish the same work by Thomas = 16 days

And the number of days required to finish the work by Charles = 17 days

Thus, the number of days required to finish the work by Joseph, Thomas, and Charles together = ?

Here a = 15 days

And, b = 16 days

And, c = 17 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Joseph, Thomas, and Charles working together

= 15 × 16 × 17/15 × 16 + 15 × 17 + 16 × 17 days

= 4080/240 + 255 + 272 days

= 4080/767 days

= 4080/767 days

= 5 245/767 days or 5.319

Thus, Joseph, Thomas, and Charles together will finish the work in 5 245/767 days or 5.319 days Answer


Similar Questions

(1) If Brenda can finish the work in 76 days and Arthur can finish the same work in 81 days, then in how many days both can finish the work together?

(2) If Anthony can finish the work in 31 days and Jeffrey can finish the same work in 36 days, then in how many days both can finish the work together?

(3) Paul can finish a work in 35 days. Andrew can finish the same work in 36 days while Joshua can finish the work in 37 days. How long will it take to finish it if they work together?

(4) Nicholas can finish a work in 69 days. Jonathan can finish the same work in 74 days while Stephen can finish the work in 79 days. How long will it take to finish it if they work together?

(5) If Elizabeth can finish the work in 11 days and Daniel can finish the same work in 14 days, then in how many days both can finish the work together?

(6) If Gary can finish the work in 67 days and Christian can finish the same work in 72 days, then in how many days both can finish the work together?

(7) If Michael can finish the work in 11 days and Thomas can finish the same work in 16 days, then in how many days both can finish the work together?

(8) If Paul can finish the work in 39 days and Larry can finish the same work in 44 days, then in how many days both can finish the work together?

(9) If Stephen can finish the work in 75 days and Carl can finish the same work in 80 days, then in how many days both can finish the work together?

(10) If Sharon can finish the work in 60 days and Zachary can finish the same work in 65 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©