Time and Work
MCQs Math


Question:     Joseph can finish a work in 15 days. Thomas can finish the same work in 16 days while Charles can finish the work in 17 days. How long will it take to finish it if they work together?


Correct Answer  5 245/767 days or 5.319 days

Solution And Explanation

Solution

Given,

The number of days required to finish a piece of work by Joseph = 15 days

And, the number of days required to finish the same work by Thomas = 16 days

And, the number of days required to finish the same work by Charles = 17 days

Thus, the number of days required to finish the work by all of them if they work together = ?

Here,

∵ In 15 days the work is done by Joseph = 1

∴ The work done by Joseph in 1 day = 1/15

Similarly,

∵ In 16 days the work is done by Thomas = 1

∴ The work done by Thomas in 1 day = 1/16

Similarly,

∵ In 17 days the work is done by Charles = 1

∴ The work done by Charles in 1 day = 1/17 part

Now, the work done by Joseph, Thomas, and Charles together in 1 day

= Joseph's 1 day work + Thomas's 1 day work + Charles's 1 day work

= 1/15 + 1/16 + 1/17

= 272 + 255 + 240/4080

= 767/4080 part of work

This means in 1 day, 767/4080 part of work is done by Joseph, Thomas and Charles working together.

Now, the number of days required to finish 767/4080 part of work by Joseph, Thomas, and Charles working together = 1

∴ the number of days required to finish the whole work (1 work) by Joseph + Thomas + Charles together

= 1/767/4080

= 1 × 4080/767 = 4080/767 days

= 5 245/767 days = or 5.319 days

Thus, Joseph, Thomas, and Charles working together will finish the total work (1 work) in 5 245/767 days = or 5.319 days Answer

Shortcut Trick to solve the problems based on time and work using formula

Case: If A can finish a work in a days, B can finish the same work in b days, and C can finish the work in c days
then working together the number of days required to finish the work
= a × b × c/ab + ac + bc days.

Here given,

The number of days required to finish the work by Joseph = 15 days

And the number of days required to finish the same work by Thomas = 16 days

And the number of days required to finish the work by Charles = 17 days

Thus, the number of days required to finish the work by Joseph, Thomas, and Charles together = ?

Here a = 15 days

And, b = 16 days

And, c = 17 days

Thus, using formula a × b × c/ab + ac + bc days

The number of days required to finish the work when Joseph, Thomas, and Charles working together

= 15 × 16 × 17/15 × 16 + 15 × 17 + 16 × 17 days

= 4080/240 + 255 + 272 days

= 4080/767 days

= 4080/767 days

= 5 245/767 days or 5.319

Thus, Joseph, Thomas, and Charles together will finish the work in 5 245/767 days or 5.319 days Answer


Similar Questions

(1) If George can finish the work in 48 days and Dennis can finish the same work in 52 days, then in how many days both can finish the work together?

(2) If Sandra can finish the work in 31 days and Gary can finish the same work in 35 days, then in how many days both can finish the work together?

(3) If Carol can finish the work in 43 days and Alexander can finish the same work in 46 days, then in how many days both can finish the work together?

(4) Brian can finish a work in 45 days. George can finish the same work in 46 days while Timothy can finish the work in 47 days. How long will it take to finish it if they work together?

(5) If William can finish the work in 34 days and Matthew can finish the same work in 50 days, then in how many days both can finish the work together?

(6) If Amy can finish the work in 68 days and Keith can finish the same work in 73 days, then in how many days both can finish the work together?

(7) Joseph can finish a work in 15 days. Thomas can finish the same work in 16 days while Charles can finish the work in 17 days. How long will it take to finish it if they work together?

(8) Helen can finish a work in 84 days. Katherine can finish the same work in 89 days while Christine can finish the work in 94 days. How long will it take to finish it if they work together?

(9) If Susan can finish the work in 15 days and Donald can finish the same work in 19 days, then in how many days both can finish the work together?

(10) If Kevin can finish the work in 47 days and Frank can finish the same work in 52 days, then in how many days both can finish the work together?


NCERT Solution and CBSE Notes for class twelve, eleventh, tenth, ninth, seventh, sixth, fifth, fourth and General Math for competitive Exams. ©